苏莎路道路工程监理实施细则苏莎路道路工程监理实施细则B11项目名称苏莎路道路工程建设监理实施细则编制专业专业专业专业专业专业审批监理机构编报时间目录第一章项目概述·······················································2第二章监理范围························································3第三章监理依据························································3第四章监理目标及工作原则··············································4第五章监理__机构及人员职责··········································5第六章监理工作内容····················································7第七章工地会议制度····················································9第八章测量放样实施细则················································10第九章路基工程施工监理实施细则········································13第十章钢筋工程监理实施细则············································20第十一章混凝土工程监理实施细则········································21第十二章钻孔桩监理实施细则············································24第十三章先张法预应力预制梁监理实施细则································29第十四章后张预应力预制梁监理实施细则··································31第十五章桥梁结构物预制__监理实施细则································38第十六章钢筋混凝土板涵监理实施细则····································40第十七章排水管网监理实施细则··········································46第十八章人行道、路缘石监理实施细则····································55第__章挡土墙、防护及其他砌筑工程质量监理实施细则····················57第__章照明、电力、管线综合工程监理实施细则··························58第__一章、交通工程监理实施细则······································60第__二章绿化、景观工程监理实施细则··································62第__三章安全文明监理实施细则
三十二、施工安全监理实施细.doc········································64第1章工程概述
一、工程名称及参建单位
1、工程名称苏莎路道路工程
2、工程地点琼海市嘉积镇、中原镇和博鳌镇之间,北起雅园路,南至规划康乐路
2、建设单位海南鳌城国际医疗旅游先行区__建设有限公司
3、设计单位天津市政工程设计研究院
4、勘察单位
5、监理单位海南新世纪建设项目__管理有限公司
6、施工单位海南第四建筑工程公司
2、工程概况
1、苏莎路道路工程位于琼海市嘉积镇、中原镇和博鳌镇之间,北起雅园路,南至规划康乐路总长约
6.177公里,双向四车道沥青砼路面建设内容包括道路工程、交通工程、涵洞工程、排水工程、照明工程和绿化工程等
2、设计标准1按照城市次干路标准,设计车速V=40Km/h2道路标准横断面K0+040~K6+
217.___如下6m人行道+非机动车道+绿化带+
7.5m机动车+
3.0m__绿化带+
7.5m机动车+6m人行道+非机动车道+绿化带=30m;3主要技术指标表主要技术指标表序号项目单位规范值设计值备注1道路等级次干路次干路2设计速度km/h
50、
40、30403车道数个——44单个车道宽度m
3.
25、
3.
53.55交通量达到饱和状态设计年限15年15年6交通等级中交通7路面结构设计基准期15年8不设超高最小圆半径m3003009平曲线最小长度m
70142.91410圆曲线最小长度m
3586.32411缓和曲线最小长度m
3565.33312停车视距m303013最大纵坡%
6.
00.7514最小坡长m11012015竖曲线最小半径凸形竖曲线m400650016凹形竖曲线m400800017竖曲线最小长度m
9090.57818桥涵设计荷载等级城-A19路面设计标准轴载BZZ-10020道路最小净高要求m
5.04其他设计荷载路面结构计算荷载为BZZ-100标准轴载交通量预测分析15年沥青混凝土路面设计使用年限10年地震基本烈度地震基本烈度VI度(Ⅶ度设防),动峰值加速度
0.1g容许工后沉降一般路段≤30cm、桥台背后≤10cm、涵洞等构造物段≤15cm、一般管线≤20cm;过渡段沉降坡差≤2‰;平面坐标系海南海口__坐标系,高程系85国家基准第二章监理范围本项目监理范围为苏莎路道路工程施工阶段的全过程监理,监理单位将严格按照监理委托合同的监理工作范围对苏莎路道路工程的道路工程、交通工程、涵洞工程、排水工程、照明工程和绿化工程等进行现场监理第三章监理依据
1、苏莎路道路工程施工图设计文件
2、苏莎路道路工程委托监理合同
3、苏莎路道路工程施工合同文件
4、《城镇道路工程与质量验收规范》(CJJ1-2008)
5、《公路桥涵施工技术规范》(JTG/TF50-
20116、《公路沥青路面施工技术规范》(JTG/TF40-
20047、《给排水管道工程施工及验收规范》(GB50268-
20088、《给排水构筑物工程施工及验收标准》(GB50141-
20089、《埋地塑料排水管道工程技术规范》(CJJ143-
201010、《公路路基施工技术规范》(JTGF10-
200611、《公路路面基层施工技术规范》(JTJ034-
200012、《城市道路照明工程施工及验收标准》(CJJ__-
200113、《城市桥梁桥面防水工程技术规程》(CJJ139-2010)
14、《市政排水管渠工程质量检验评定标准》CJJ3-
9015、城市供水排水工程建设标准强制性条文
16、《城市绿化工程施工及验收规范》CJJT82-
9917、《城市桥梁工程施工与质量验收规范》(CJJ2-2008)
18、《建设工程监理规范》GB50319-
201319、建设单位、监理工单位、施工单位、设计单位、勘察单位在施工过程中的有关的图纸会审记录、会议记录、工程变更等达有效协议第四章监理目标及工作原则
1、监理目标本工程监理的目标控制为,实现工程项目的投资控制,使本工程的投资不超预定目标,实际建设周期不超计划总工期工程质量总目标;争创同类项目全省一流水平,工程质量达到交通部《公路工程质量检验评定标准》中工程质量优良等级的要求,所有竣工单位工程全部达到合格标准,且优良率达到90%以上分项工程验收优良率达到95%且合同段的工程质量评分值不小于90分;主要分部工程达到优良,并力争单位工程优良率达到95%以上,力争做到无工程质量事故安全监理总目标施工单位职工工伤死亡率为0,工伤率不超过
0.04‰,监理人员无伤亡事故施工单位万元以上的直接经济损失控制在年产值的
0.4‰以下施工过程环境保护达到国家标准
2、工作原则本工程监理实行“总监理工程师负责制,专业监理工程师责任制”施工监理工作要求“法制化、标准化、规范化、程序化”一切监督管理工作要依据__的有关法令、法规、施工承发包合同和监理合同,以实现法制化;质量控制以规范、规程、设计文件、数据为依据,实现标准化;统一记录、报表格式,实现规范化;执行监理工作流程进行监理,实现程序化,以实现合同目标第5章监理__机构及人员职责
一、监理__机构__机构图
二、监理人员责任总监理工程师职责
1、确定项目监理机构人员的分工和岗位职责;
2、主持编写项目监理规划、审批项目监理实施细则,并负责管理项目机构的日常工作;
3、审查分包单位的资质,并提出审查意见;
4、检查和监督监理人员的工作,根据工程项目的进展情况可进行人员调配,对不称职的人员应调换其工作;
5、主持监理工作会议,签发项目监理机构的文件和指令;
6、审定承包单位提交的开工报告、施工__设计、技术方案、进度计划;
7、审核签署承包单位的申请、支付证书和竣工结算;
8、审查和处理工程变更;
9、主持或参与工程质量事故的调查;
10、调解建设单位与承包单位的合同争议、处理索赔、审批工程延期;
11、__编写并签发监理月报、监理工作阶段报告、专题报告和项目监理工作总结;
12、审核签认分部工程和单位工程的质量检验评定资料,审查承包单位的竣工申请,__监理人员对待验收的工程项目进行质量检查,参与工程质量的竣工验收;
13、主持整理工程项目的监理资料总监理工程师代表职责
1、负责总监理工程师指定或交办的监理工作;
2、按总监理工程师的授权,行使总监理工程师的部分职责和权力专业监理工程师职责
1、负责编制本专业的监理实施细则;
2、负责本专业监理工作的具体实施;
3、__、指导、检查和监督本专业监理员工作,当人员需要调整时,向总监理工程师提出建议;
4、审查承包单位提交的涉及本专业的计划、方案、申请、变更,并向总监理工程提出报告;
5、负责本专业分项工程验收及隐蔽工程验收;
6、定期向总监理工程师提交本专业监理工作实施情况报告,对重大问题及时向总监理工程汇报和请示;
7、根据本专业监理工程工作实施情况做好监理日记;
8、负责本专业监理资料的收集、汇总及整理,参与编写监理月报;
9、核查进场材料、设备、构配件的原始凭证、检测报告等质量证明文件及其质量情况,根据实际情况认为有必要时对进场材料、设备、构配件进行平行检验,合格时予以签认;
10、负责本专业的工程计量工作,审核工程计量的数据和原始凭证监理员职责
1、在专业监理工程师的指导下开展现场监理工作;
2、检查承包单位投入工程项目的人力、材料、主要设备及其使用、运行状况,并做好检查记录;
3、复核或从施工现场直接获取工程计量的有关数据并签署原始凭证;
4、按设计图及有关标准,对承包单位的工艺过程或施工工序进行检查和记录,对__制作及工序施工质量检查结果进行记录;
5、担任旁站工作,发现问题及时指出并向专业监理工程师报告;
6、做好监理日记和有关的监理记录第六章监理工作内容
一、工程施工质量监理
1、工程质量监理的基本程序现场监理对承包人的各项施工程序、施工方法和施工工艺及材料、机械等进行全方位的巡视,重点部位及关键工序采取全过程旁站、全环节检查,以达到对施工质量有效的监督管理总监理工程师或总监理工程师代表应经常巡视工地,各专业监理工程师应每天巡视施工现场,发现并处理施工质量问题;现场监理工程师及助理人员对隐蔽工程及中要工程部位、重要工序及工艺进行全过程旁站监理,及时消除影响工程质量的不利因素应在每道工序结束后,及时进行检查和进行现场监施工单位技术人员按规定频率抽取试样,并做好施工记录在各项工程施工过程中,或缺陷责任期内,如发现有技术标准、技术规范或设计文件所不允许的质量缺陷或质量事故时,专业监理工程师要向总监理工程师或总监理工程师代表汇报,并及时指令施工单位进行修补或返工,使之满足质量要求,未经修复或达不到质量标准的不得进行下道工序和分项工程的施工,情况严重的应汇报总监理工程师,总监理工程师核实后,报建设单位必要时由总监理工程师发出工程暂停令,责令停工整改,对不合格的工程不予计量工程量如有必要时根据合同文件的规定,建设单位可以雇佣其他施工队伍进行修复或返工,其费用从原施工单位的款项中扣除对于工程质量事故,现场监理工程师应要求施工单位尽快提出事故报告,并汇报总监理工程师和建设单位同时,总监理工程师应会同建设单位__有关人员进行调查、测试分析,并审查施工单位提出的工程缺陷和事故处理方案,在总监理工程师审批并经建设单位同意后,由施工单位按批准的方案进行修复或返工未经批准而自行处理的,不予计量支付和验收
二、工程进度监理施工单位应及时编制工程施工总体计划及必要的各项关键工程进度网络图、有关施工方案和施工方法及说明、全部支付的现金流动估算报等报监理单位审查,经监理单位审查后,报建设单位审核承包人根据批准的总体进度计划,在项目开工前,编制工程施工阶段性的月进度计划和更加详细的周施工进度计划,做到施工进度控制心中有数施工单位在施工过程中,监理工程师要经常检查和监督计划的实施情况,进行动态跟踪分析、比较,如发生偏离,要及时提醒施工单位分析原因,并采取有效措施,协调各方关系,加快工程进度,或调整修改计划,以保证事项阶段性目标和总进度目标对加快工程进度所采取的措施,方案及修正计划均应经总监理工程师及建设单位审批施工单位工期的延误的,虽然采取了措施,但仍然不能实现阶段性进度目标和总体目标,或拒绝执行总监理工程师及建设单位的加快施工进度的指令,监理单位应发出书面警告,并及时报建设单位决策监理单位要检查施工单位按单位工程、分项工程的每日实际进度记录和每月进度分析报告,及时掌握工程动态和影响工程进度的不利因素,作为调整和修改计划的依据
三、工程投资控制监理工程计量按照合同条件、工程量清单、设计图纸、工程变更文件等规定的内容、范围和单位进行计量计量时先由施工单位在规定时间提出计量申请,必须附有相关资料,经监理单位审查有关准备资料合格,双方到现场共同计量后,监理单位审查、签认实际完成工程量对资料不齐全或发现有质量问题的工程暂不计量,对不符合合同文件要求的工程不得计量,对于监理工程师认可的,或批准的工程,即使施工单位不派人到现场测量,也可作为支付依据据实计量是根据图纸、变更设计资料、相关规范要求等对现场施工完成的工程进行计量工程款支付应在合同实施期间对工程的前期支付、中期支付和最终支付的所有应支付的项目都必须按照合同文件和有关规定的程序,由施工单位提出有关报表和申请,经监理单位审查、确认扣除应扣款项后,由总监理工程师审核,并提出审核意见,报建设单位审批后签发支付证书单价调整按照合同规定执行,计日工的使用必须经监理工程师批准,计日工按合同单价计费,缺项的单价由承包人按其投标报价及单价分析的原则、内容和费用结合合同的有关规定进行计算和编制,报监理单位,监理单位提出书面审查意见,报送建设单位批准执行
四、合同管理依据合同文件对合同执行过程进行监督管理在合同实施过程中,妥善解决合同管理范围内的工程变更、工程延误、费用索赔、违约、争端、分包等问题,对保证工程进度、确保工程质量和合理投资等,都具有十分重要意义工程变更是合同管理的重要内容之一,同时也是施工阶段影响费用控制的重要因素一般情况下,除工程地质条件变化或原设计存在明显缺点外,均应按设计施工图进行施工,不要轻易改变原施工图设计工程变更可以由建设单位、设计单位、监理工程师和承包人中的任何一方提出在本项目中,工程变更分为小型变更、一般变更、重要变更、重大变更等类型,不同类型的变更按业主授权的有关规定进行处理,所有变更均须设计单位或其代表同意,并出具变更图工程延期指竣工期的延长,一般是不允许发生的但如果发生,则按照合同文件的有关规定程序__由施工单位提出申请,建设、监理单位进行调查、协调评估后审定批准,非施工单位责任的或不可抗拒的客观条件引起的延期,应按合同有关规定和程序执行;如延期属施工单位责任,施工单位则应按合同有关规定向业主支付延期损失补偿金第七章工地会议制度高度会议根据会议召开的时间、内容及参加人员的不同,主要分为工地例会和现场专题会两种形式第一次工地会议由建设单位主持建设单位、承包单位和监理单位分别介绍各自驻现场的__机构、人员及其分工建设单位根据监理合同宣布对总监理工程师的授权建设单位介绍工程开工准备情况承包单位介绍施工准备情况建设单位和总监理工程师对施工准备情况提出意见和要求总监理工程师介绍监理规划的主要内容(监理工作交底)研究确定各方在施工过程中参__地例会的主要人员,召开工地例会周期、地点及主要议题目的在于工程开工前对各方、各项准备工作进行全面的检查、确保工程实施有一个良好的开端后续工地例会由监理单位支持,按照第一次工地会议确定的各单位参加人员及召开时间、地点等召开高度例会讨论协调工程施工情况、工程施工进度、施工技术问题等,为工程的顺利实施做好事前、事中、事后控制现场专题会是在工程出现需要协调沟通解决的问题时临时召开的各类专题会议,应根据具体情况定期或不定期召开,会议对近工中遇到的问题及需要协调解决的问题等进行讨论、协调和解决,对发现的施工质量问题及时予以纠正;对于影响施工的各类事宜及时予以协商解决第八章测量放样监理实施细则测量工作要贯穿施工的全过程,是监理工程师质量控制的重点之一,因此监理工程师在施工各阶段要加强测量工作的检查,测量工作一旦失误,会造成很严重的后果,给工程带来严重的经济和工期损失对放线依据、基准点、基准线须要经过严格检查
一、测量监理控制程序框图
2、测量监理的依据
1、依据设计单位提供的施工图纸设计资料,及有效的变更设计文件等
2、公路勘测规范—JTJ061-
993、路桥位勘测使用公路勘测规范—JTJ061-
994、公路路基施工技术规范—JTJ033-
955、公路工程施工监理规范-JTJ077-
946、工程测量规范(国家标准)-GB50026-93
三、监理工程师测量放样阶段的职责
1、在总监理工程师的__下,严格按照规范要求的进度监督承包人放线、放样,审查或批准承包人测量的外业成果及道路和构造物的几何尺寸、标高等
2、复杂检查承包人对水准点及其它控制点的护桩设施,保证不受损坏,有变更时需在图上标明
3、不断检查承包人的测量放样工作,随时抽查各项测量记录,要认真核对,确认后签认
4、审查承包人的检查申请,经现场检验校核后,符合规范要求的精度后方能签字,否则应将所有不合格部分及时通知有关人员
5、检查路基工程的土石分界线,并督促承包人标绘在横断面图上
6、协助合同工程师、道路工程师和结构工程师做好工程的计量工作,检查中期支付申请
7、定期监督检查承包人使用的仪器的精度
四、监理对测量放样质量的监控与要求
(一)在公路工程建设中,其工作内容有
1、在工程开工前,要做好引点,制作控制点、控制桩、确认各个控制点无毁坏、位移、沉降,确认书面资料记录正确无误后,才能作为施工放样的依据,进行施工放样
2、对设计资料上的中桩、桥梁、涵洞等放样点的坐标高程进行计算核对,防止因计算差错等,造成施工错误
3、通过测量手段,在高程施工的实地,准确放出施工控制点,在施工过程中进行核对,保证各施工面位置标高在允许的误差范围内
(二)工程测量监理必须做好
1、对施工单位的测量设备进行检查,测量仪器需具有合格的校准检验证书,方可进场使用
2、了解施工单位测量人员的测量资格情况,及测量的操作,程序和方法必须正确,查看测量原始记录,及时发现问题解决问题
3、同施工单位一起复测各填挖断面的地面线,保证结果的真实性
4、检查复核施工单位上报的测量放样资料,对重要的放样测量进行旁站证实,正确无误后给予确认
5、每个单项工程完工后,检查其坐标和标高,测出偏位和误差情况,合格后给予确认,进入下一道工序
6、与施工单位的质检人员密切配合,对测量放样工作实时监控,帮助测量人员提高施工放样的质量减少误差,把好质量关
(三)公路测量放样的偏差必须在允许范围内,如的设计文件中有特别要求提高精度的应按设计要求执行
1、各施工阶段允许偏差表土方路基检查项目允许偏差检查项目允许偏差纵断高程(mm)+10,-20平整度(mm)≤20中线偏位(mm)±100横坡(%)±
0.5宽度不小于设计值边坡(mm)不陡于设计值石方工程检查项目允许偏差检查项目允许偏差纵断高程(mm)+10,-30平整度(mm)30中线偏位(mm)±100横坡(%)±
0.5宽度不小于设计值边坡(mm)坡度不陡于设计值平顺度符合设计要求涵洞通道的允许偏差检查项目允许偏差检查方法轴线偏差(mm)明涵±20暗涵±50全站仪坐标检查高程检查(mm)明涵±20暗涵±50水准仪高程观测桥梁工程成桩检查检查项目允许偏差检查方法桩位群桩100mm用经纬仪检查纵横方向排桩50mm桥梁工程上部放样检查检查项目允许偏差检查方法轴线偏差mm±10全站仪坐标放样顶面高程mm±10水准仪实测标高
五、测量放样内业资料的收集与管理
1、施工单位在开工前进行包括导线、中线的复测,水准点的复测与增设,横断面的测量与绘制等,监理工程师参加此项工作,对于设计资料不符合的部分进行复测并作出结论
2、在施工单位对所有测量记录计算资料整理后,由施工单位的测量员及主管技术人员共同签字后,测量监理工程师进行核查,其测量成果批准后作为本工程的依据资料存档管理
3、工程的开工及分项工程开工以前进行施工放样,填写报验单和质检报告,监理工程师进行检查和确认,放样数据和坐标、高程资料等要存档第九章路基工程施工监理实施细则
一、技术要求
1、路基概况项目起点接规划雅园路,向南展线,终点与规划康乐路平交,路线全长约
6.177Km,路线走向与规划路线基本一致,局部路段根据实际地形及现状农田的情况进行避让,通过适当的线形组合,设计出合理线位,全线共设7个平曲线转点,圆曲线最小半径300m,最大圆曲线半径1300m红线宽度30m起点坐标(海南平面坐标系)为X=121__
7.469,Y=
211004.751终点坐标为X=
117070.108,Y=
214492.760道路纵断面主要受规划标高的控制,道路最小排水纵坡度采用
0.3%本标段共设竖曲线22处,最大凸型竖曲线半径R凸=22000m;最小凸型竖曲线半径R凸=6500m,最大凹型竖曲线半径R凹=16000m;最小凹型竖曲线半径R凹=8000m,详见本标段《道路纵断面图》道路纵断面设计高指__分隔带侧石下路面高程;路口处纵断面设计高为相应位置路面高程,平交口处设计高详见各有关平交口竖向设计图苏沙道路纵坡的技术指标路线全长米:6177最小纵坡%:
0.300最大凹形竖曲线半径米:
16000.000最小凹形竖曲线半径米:
8000.000最大凸形竖曲线半径米:
22000.000最小凸形竖曲线半径米:
6500.000最小竖曲线长度米:
47.__3道路标准横断面K0+040~K6+
217.___如下6m人行道+非机动车道+绿化带+
7.5m机动车+
3.0m__绿化带+
7.5m机动车+6m人行道+非机动车道+绿化带=30m;
2、技术要求填方路基本项目填方路基为少占基本农田或地面横坡较陡、填方较大时,采用钢筋混凝土挡土墙进行收坡支挡,其余段采用放坡的方式填方边坡高度≤8m时,边坡坡率取1:
1.5;边坡高度>8m时,采用折线形式上部
8.0米取1:
1.5,下部取1:
1.75挖方路基本项目挖方路基较少,仅部分路段有挖方,且挖深均小于1m,采用放坡的方式慢行系统外侧设置
0.6x
0.6m浆砌片石矩形边沟挖方边坡高度均小于1m,挖方边坡坡率取值为1:1道路横披采用直线型路拱,一般路段车行道横坡向外
2.0%;人行道横坡向内
2.0%填挖交界处理为了保证填挖交界段路基、路面的整体稳定性,减少路基的不均匀沉降,填挖交界处须开蹬搭接处理先清除松散表土再开挖台阶,台阶高度
1.0m,宽度不小于
2.0m,设4%内倾的坡度,并采用小型机械夯实,压实度不小于90%横向填挖交界对挖方区路床80cm范围内土体超挖并在路床底部铺设1层10m宽玻璃纤维格栅搭接,路堤上部的2个台阶上分别铺设
4.0m宽玻璃纤维格栅对于横向填挖交界处,当填方部分不足一个行车道时,应超挖至一个行车道宽度纵向填挖交界对挖方区路床80cm范围内土体纵向超挖10m长并在路床底部铺设1层20m宽玻璃纤维格栅搭接,路堤上部的2个台阶上分别铺设
4.0m宽__玻璃纤维格栅为保证路基处于较好的水文条件,在纵向沿填挖交界处设置碎石盲沟把裂隙水或下渗水引出路基,以保证路基安全填挖交界处应设置过渡段,待填筑至路床底部后,应采用冲击式振动压路机进行增强补压,以削减路基填挖间差异变形,在有管线部位采用人工压实,并注意管线的保护地基处理根据地质勘查报告,苏莎路在K0+960~K2+050段存在淤泥质土,层厚为
4.0~
5.2m,其上为
5.1~
6.0m的粉质粘土+
0.5m厚的人工填土;K3+710~K4+820及K5+680~K6+070段道路沿线存在层厚为
0.6-
1.0m的人工填土、种植土层,其下为粉质粘土及中粗沙层淤泥质土所处桩号范围内无大型构筑物,仅有部分圆管涵及2×2m的箱涵,且软土层上部均覆有5m以上的粉质粘土层,无需对该淤泥质土层进行处理对于人工填土、种植土层,采用浅层换填处理浅层换填处理适用于K3+710~K4+820及K5+680~K6+070段,对现状地基清表后再进行换填处理1)换填材料沿线均位于地下水位以上采用符合填料要求的一般土回填2)换填厚度清表后的人工填土、种植土层厚度,不小于50cm3)换填宽度填方路段处理范围应超出路堤坡脚100cm以上的宽度;零填及挖方路段处理范围应超出路基外边缘100cm以上的宽度4)换填路堤用土应在最佳含水量±2%范围内分层摊铺压实,压实度不应低于路基规定或特别指定的压实度一般路基填筑
(1)路基施工前应将原地面的草皮、树根、杂物等全部清除干净,并大致找平压实,压实度不小于90%(重型压实标准)路基施工应注意保护生态环境,清除的杂物应妥善处理,不能倾倒于河流水域中
(2)路基必须分层填筑碾压每层最大压实厚度不超过30cm,路床顶面层最小厚度不小于10cm,含水量应控制在压实最佳含水量±2%之内考虑苏莎路为园区重要的进出场道路,为保证路基稳定及减少沉降,将路基压实度及其它有关要求按主干路标准进行控制,具体要求见下表路基填料最小强度、压实度及最大粒径要求项目分类路面底面以下深度(m)填料最小强CBR(%)压实度(%)(重型击实)填料最大粒径(mm)路床0~
0.38≥
951000.3~
0.85≥95100上路堤
0.8~
1.54≥94150下路堤
1.5以下3≥92150零填及路堑路床0~30cm8≥94100
二、监理程序框图监理程序施工程序
三、土方开挖填筑
1、审查承包人提交该路段的施工方案、施工计划、自检系统及保证措施;
2、现场核实开工路段长度、路堤类型、填料质量及堆放位置、各种机械型号和台数、试验测试设备等
3、测量放样1)核查承包人的内业成果资料2)抽检路基中线、水平及边坡坡率是否在允许范围内3)核签填前碾压后新测绘的填方标准横断面图(50m一个)
4、检查施工现场的清理工作1)检查路__表处理草皮腐殖土等应推除,树根全部挖除,清除灌木丛、垃圾、泥炭及有机物杂质,坑穴夯平2)检查填筑前碾压路堤基底应在填筑前整平碾压,压实度不小于90%
4、土质填料的检查1)要求施工单位每5000m3或土质变化时取样,按JTJ-051-93《公路土工试验规程》规定的方法做的试验检测并现场书面资料;2以15%的规范频率抽检填料质量,检查选料是否符合要求3)要求施工单位进行干密度试验,确定每种土样的最大干密度和最佳含水量4)审批施工单位在开工28天前进行的现场压实试验结果,确定填料松铺厚度、碾压遍数、碾压速度及压实设备类型、组合方式等正确的压实符合和施工控制标准
5、分层填筑的质量控制1)严格控制填料机械摊铺,尺检分层厚度,每层最大压实厚度不超过30cm,路床顶面层最小厚度不小于10cm,把好平整度、路拱度,确保层面平顺不亏坡;2)根据天气变化,监督施工单位采取翻拌凉晒或洒水,控制土料的含水量在最佳含水量的±2%范围内,确保压实效果;3)填料压实后,每层都应由施工单位自检及在监理人员见证下取样送检检测,才允许施工单位进行下一道工序(即上一层填土)施工
6、路基工程的验收1)分析复核施工单位提交的报验申请表和自检资料2)共同或单独去现场抽检各项指标是否达到要求3)签认路基工程质量报验申请表
四、路基工程施工主要注意事项
1、填土路基重点检查土质填料的质量和分层压实度应符合要求,不合格填料必须推除;松铺厚度应控制好,不得偏厚;填料应翻拌凉晒或洒水至规定含水量,不得过湿或过干;碾压工序、机械压实遍数和速度应按监理工程师批准的标准进行,直至压实合格
2、填石路基填石路基应石块逐层水平填筑,分层厚度约30-50cm,石质坚硬可适当加厚,石块最大尺寸超过压实厚度的2/3,所有细缝填以小石块或石屑,边坡要求码砌加固压实度一般由现场试验确定的压实遍数控制,直至压实层稳定,无下沉,石块紧密、表面平整无车辙
3、土石路基土石混合材料不得采用倾填法施工,宜按30-40cm(经试验后确定)的松铺厚度进行分层填筑,并避免较大的石块集中压实度由现场试验确定的压实遍数控制,检查时碾压不出现石块转动,表面平整均匀
4、结构构筑物底的回填回填材料应选用砂砾、碎石土等渗水材料,粒径不超过5cm含有淤泥、杂草、腐殖物的土不得使用回填应分层填筑,每层松铺厚度为15-20cm控制压实度为95%在压路机不到的地方,应使用小型机动夯具或冲击夯压实
5、挖方地段为保证挖方段的边坡稳定,应要求承包人选择合理的开挖方法,按设计做好边坡坡率和边坡防护工程,保证坡顶稳定零填、填挖交界及路堑上路床0-30cm应充分碾压如大不到压实度要求,应翻松晾晒或换填,直至分层压实合格开挖中出现石方时,应测量土石分界线,点绘在横断面图上第十章钢筋工程监理细则
一、原材料试验
1、施工单位应钢筋原材料机械检测报验验收,并在监理人员的见证下机械取样送检
2、原材料的出厂证明、检验单、质保单等质保资料应齐全
3、经监理工程师验收合格后,钢筋原材料方可使用
二、原材料进场储存主要检查存放是否支垫好或放在格架上,有无覆盖遮挡,是否远离油脂、油漆、灰尘等到杂物,以免锈蚀污染
三、检查焊接情况
1、检查原材料的可焊性,主要检查其抗拉强度、延伸率、抗弯等性能的检测情况,是否符合规范要求
2、检查焊接工艺,外观要求能否达到,检测结果是否合格
四、钢筋材料的验收程序钢筋材料进场后施工单位要在监理人员见证下进行取样送检,在同批取样抗拉、延伸率、冷弯性能各取两根(共6根)若合格,则钢筋可用,若不合格,再加倍取样合格可用;若不合格,则该批钢筋不得使用焊接,可采用闪光对焊或电弧焊,每200个接头为宜批每批取6个试件,3个做拉伸试验,3个做冷弯试验若合格,认为该批钢筋可用,若不合格,重复双倍取样试验,合格仍认为该批合格,否则该批为不合格
五、钢筋笼入模钢筋入模后,监理要检验钢筋是否齐全,编号规格有无遗漏,支架垫块是否合格牢固,保证保护层措施,能否抵御浇筑和振捣施工而不致移位,绑扎接头,焊接钢筋的搭配,间距等是否符合要求,各钢筋位置是否正确,尺寸是否在允许误差范围内,钢筋弯曲编排是否与图纸相符重点是主筋位置、长短、弯起、弯钩及保护层等第十一章混凝土工程监理细则
1、原材料本工程采用商品混凝土,混凝土原材料水泥、砂、碎石等,需混凝土搅拌站提供相关质量证明质量
1、水泥要有出厂证明、质保书(检验单)抽检项目水泥强度、凝结时间、安定性试验等;抽检频率200T为一批,不足200T仍为一批,每批取样一次以上
2、砂测定含砂量,硫化物、硫酸盐含量及有机物含量紧密干密度、颗粒级配、细度模量(相差不超过
0.2),应符合规范要求
3、碎石应检验压碎值、级配、针片状含量符合规范要求
4、砂石材料的质量检验应按批进行,产地和规格为一批,每批数量为200m
35、水饮用水可直接使用,其他水源要按《公路工程水质缝隙操作规程》进行检验,符合要求的水,即可批准使用
6、外掺剂按照混凝土配合比要求进行使用
二、审查混凝土配合比情况,审查搅拌站资质等情况施工单位报送配合比应有各种集料的配合比及混合后级配、曲线集料与水泥的重量比、水与水泥重量比、外掺剂用量比例、原材料来源及各项指标此外,还应有采用的通用限界、混凝土浇筑与养护混合、混凝土的和易性及塌落度混凝土搅拌站,各项材料的计量器应合格,是否按规定进行了标定,特别是经过改装的秤量装置其次要检查台秤的附近有无备用材料,有无装卸料的工具,以备增减调节料量在混凝土拌和过程中要经常抽查过秤情况,严防不经检测直接使用并且还要检查秤量周围有无材料卡秤现象,以防秤量不准
三、检查混凝土的支架和模板
1、施工脚手架应有足够的刚度,施工脚手架的支点间跨中绕度应不超过跨度的1/270,且不超过20mm
2、施工单位应向监理工程师报送一份施工脚手架的计算书,详细说明所有的设计假定,以及应力、变形、稳定性等方面的详细分析,包括结构的拱度、标高施工脚手架下应有足够的排水设施,以排雨水,防止冲刷
3、监理工程师检查现场浇筑或预制构件使用的模板时,要首先检查材料的质量模板、模具应尺寸准确,有足够的强度和刚度,以保证在混凝浇筑过程中模板牢固且无明显变形,在受到打击或拆除时不致损坏混凝土所有模板接触缝均应布置在监理工程师同意的水平或垂直面中,且应严密不漏浆在浇筑混凝土前,应检查模板是否清扫干净,模板上黏附的混凝土应全部清扫干净模板在未经检查批准,不得浇筑混凝土,未浇混凝土以前应检查钢筋入模和模板尺寸位置
四、钢筋入模钢筋在按前述方法进行原材料测试__后,在模板支立过程中入模,入模后监理工程师应注意检查钢筋有无遗留,预留保护层厚度及支架是否牢固,钢筋表面是否洁净,有无粘染油脂或脱模剂,如有应先除净还要检查模板中有无杂物,是否清除干净,最后装好封模浇筑混凝土(详见钢筋细则)
五、混凝土运输应使用混凝土罐车进行运输如采用其他形式运输应经监理工程师批准混凝土采用泵送浇筑时开始泵出润管用的的混凝土砂浆应予废弃,不得浇筑在混凝土结构中直至泵出的混凝土和易性、坍落度等符合要求后,经监理工程师认可后方可进行浇筑
六、混凝土的浇筑和振捣混凝土的浇筑程序和方法,应提前报监理工程师批准,一般在开工报告中写明浇筑后的混凝土模板或突出钢筋不得以任何方式扰动混凝土应白天浇筑,必须在夜间浇筑时,应有足够的照明设施,并经监理工程师批准在浇筑过程中必须经常地进行混凝土的坍落度试验,工地试验的坍落度应在允许范围之内,才准于入模使用坍落度不符合要求时,监理工程师应拒绝使用混凝土工程每一部分浇筑日期、时间及浇筑情况,都应有完整的记录,以备随时检查混凝土应用振捣器充分振实,完成的混凝土工程应是无空隙、不离析、无蜂窝的均匀体,拆模后显示光滑的平面振捣时应确保混凝土的各个部分都受振动,且不发生离析过振,振捣器不应于钢筋直接接触,尤其是延伸到初凝的混凝土里面的钢筋振捣器应至少有1/4备用
七、混凝土的养护混凝土在浇筑后应至少在连续7天内浇水或其他方法养生,保持表面湿润应采取覆盖、不断洒水、涂养生剂等措施
八、混凝土的强度检查混凝土试件的制取、浇筑、养生及试验,均应全过程监督或旁站制作试件应是随机的,监理工程师也可指定随机抽样工地为了控制拆模或进行预应力张拉工艺,应多制几组试件与构件同条件养生,随机测试但验收应以标养为准试验频率每构件至少取两组大体积混凝土每80~200m3或每一个工作班应制取2组按技术规范制取
九、混凝土的外观检查外观检查标高线位是否与图纸相符,外观尺寸是否合格,表面有无蜂窝麻面、跑模、漏浆等现象;外露部分颜色是否一致,钢筋有无外露,平整度是否符合要求
十、混凝土的施工缝一般施工缝都是水平或垂直平面,避开最大剪力断面如果在图纸以外位置预留施工缝时,应取得驻地工程师同意施工缝在继续浇筑时,一定要把前面浇筑的混凝土表面刷毛或凿毛,用清水闷湿润透,但不得有积水,然后涂以与原混凝土同等的水泥和水灰比的净浆再进行混凝土浇筑继续浇筑时,应经常检查原有混凝土不得使之形成开裂,否则应找出原因,拆除新旧混凝土清除开裂根源,重新浇筑第十二章钻孔桩监理实施细则
一、技术要求
(一)原材料
1、混凝土用钢筋、水泥、砂石、水、外加剂及混凝土的配比设计见相关监理实施细则
2、为便于水下混凝土的浇筑,集料宜用卵石时也可使用级配良好的碎石
3、粗集料最大粒径,卵石为40㎜,碎石为35㎜
4、严格按照设计配合比要求使用外加剂
5、若图纸上规定需要用抗硫酸盐水泥以抵抗硫酸盐侵蚀时,必须使用抗硫酸盐水泥
6、混凝土坍落度处于150-220㎜之间
(二)钻孔视当地土壤情况,钻孔可用旋转钻或冲击钻钻孔上面__的短护筒应高出原地面至少
0.3m,当在水中钻孔时筒内水位要超过外部水位至少1m,护筒顶应高出地下水位
1.5m以上,以便护壁为稳定钻机,井内应充满泥浆,泥浆密度
1.05-
1.6/M3,粘度为16-28在新旧钻孔相距5m以内的桩的钻孔与挖土,应在邻桩浇筑混凝土24小时后或另一桩尚未开钻前进行钻孔必须连续作业,不得间断钻孔中注意排除钻渣,注意保持泥浆密度和粘度,避免造成糊钻或由于坍孔造成埋钻钻孔完成后要进行清孔,即用稀泥浆压入钻锥,钻锥应从井底提起10-20㎝空转循环,此时应注意维持
1.5-
2.0m的水头代替泥浆护壁,使钻孔稳定清孔前后要对钻孔进行检查,孔的平面位置在各方向的误差均为50㎜,钻孔直径应不小于桩的直径,倾斜应不大于竖孔深的1/100,摩擦桩井底沉淀应不超过30㎝且应小于直径的
0.4倍嵌岩桩沉淀应小于5㎝
(三)放置钢筋钢筋材质应符合规范要求,钢筋应按图纸要求预先__制作成钢筋笼为保持钢筋有必要的保护层,在环筋上可加做保持保护层用的支筋或轮式垫块,其中以采用轮式垫块为宜垫块应绕周边制作,上下两层应间隔开,使钢筋笼入孔后不致放到一边陷入泥中,造成露筋如无较高的起重设备,可允许钢筋在纵向用帮条焊接上,但同一截面上的钢筋接头应不超过总横截面__的50%所谓同一截面即两拼接点中心距离应大于30倍钢筋直径,帮条钢筋的横截__应不小于主拉钢筋断面的
1.2倍在联接钢筋笼时,必须先固定好,防止受混凝土上托漂浮或不适宜的下沉
(四)浇筑混凝土钻孔成孔、放置钢筋笼后即可二次清孔,清孔后泥浆指标比重大于
1.08小于
1.2,含水率4%沉浇后嵌岩桩小于5㎝,摩擦桩小于30㎝进行混凝土或水下混凝土浇筑,浇筑水下混凝土时必须用螺栓联接的、直径不小于20㎝的导管输送,混凝土的浇筑一经开始就不能中断因此,必须备有足够的原材料、搅拌运输设备及工具等到,并应准备发电机,以防中途停电每一盘混凝土可用同等的水灰比多制备一些砂浆(如10%),用以使要使用的各项工具都沾满水泥浆浇筑时首先在导管未端加以封闭,封闭可用导管防水切断器,也可用木球、混凝土球或蓝球球胆以此8#铅丝吊住,球用混凝土压下去,铅丝的强度应能承受满导管混凝土的重量,导管距孔底20-40㎝在导管和其上面的灌灰漏斗都装满混凝土后,剪断铅丝使混凝土压球从导管底部输出,导管中应没有水进入,导管中的所有连接头垫有橡胶片,因此导管是不透水的随后应陆续加入混凝土,使导管和漏斗总是充满混凝土,并随时检查导管外的混凝土面,保持导管出口经常插在已浇的混凝土中长度不少于2m随着混凝土面的升离,不断拆除导管的分节导管口应始终插在浇出水面的50-100㎝,混凝土应当全部出水并在成桩后将多余的混凝土剔掉,打开钢筋,将桩头插入承台内水下混凝土每浇筑50M3,应制取一组三块混凝土试件且每根桩至少取二组进行标准养生,用以检验其强度从钻孔、成孔、浇筑水下混凝土至成桩都必须有完整的记录,以备监理工程师审查
(五)桩的试验检测为了验证设计的正确性和施工质量,应按照设计及规范要求对桩基工程进行试验,即进行静载试验、检验性荷载试验、动测、超声波检测等
二、监理程序监理程序见图7-5钻孔桩监理程序监理程序施工程序、
二、施工监理程序
1、施工单位根据图纸进行放线,确定桥位、墩位、台位和桩位监理工程师的主要工作是复核放线测量是否达到规范要求,然后复核一次各墩台是否正确实践表明施工中必须认真确定桩位
2、其他准备工作备好材料、机具,做好混凝土的配比设计并报监理工程师审核批准监理工程师应__人力取样抽验核对原材料及机具落实情况,并核对水泥混凝土配合比例,要特别注意配比的坍落度
3、施工单位在做好一切准备工作后即可提出桩基的开工报告,包括开工日期,预计竣工日期,施工进度计划,机具、材料准备情况,人力、电力的准备情况,以及放线定位和试桩的结果等经监理工程师__审查落实,认为合格后即可批准开工
4、桩基开工后,首先是钻进成孔并清孔,在此施工阶段,监理工程师应进行旁站检查,经常了解钻进情况、泥浆情况及土层情况,清孔后要测井深看沉淀量是否合格,同时要检查井深、井径和倾斜度是否合格,还要注意检查清孔后井中泥浆的密度和粘度
5、下钢筋笼和焊接监理工程师应注意钢筋是否栓牢,焊接是否完整,上下接点距离是否达到30d的距离钢筋最后应固定在设计位置,既不能上浮,也不能下陷
6、下管道灌水下混凝土导管应预先试接,并作水密性、气密性试验接口应严密、基本不漏水,导管最下一节应用无法拦管,以免挂住钢筋使导管提不起来导管应位于桩的中心,亦即钢筋笼中心,以避免与钢筋相碰,管口应插入已浇混凝土中1-6m,一般以2m为宜浇筑的混凝土要经常检查其坍落度,这项试验主要由承包商的试验员自检,监理人员应随时抽检,坍落度过小影响混凝土的流动度,太大表示水灰比过大影响强度导管应从上面逐步减短,并应随时检查混凝土面标高,以保证导管插在混凝土内,使混凝土不致中断导管内混凝土面一定要保持一定高度,勿使导管内窝住空气造成高气压囊井筒内水面一定要保持高于井外水面,以防孔壁坍塌混凝土浇筑到超过设计高度
0.5-
1.0m,超高部分应在做桩帽承台前予以凿除混凝土浇筑应做好记录
7、浇桩完毕,混凝土硬化合格后应进行无破损探查此项试验应由有资质的单位来进行,该部门应经监理工程师检验其资格证件并批准后方可进行工作
8、在混凝土试养生期满后应规范进行混凝土强度检查每根灌注桩或每浇筑50M3混凝土应有一组试件
9、当监理工程师认为桩基可能有缺陷时,可要求承包商钻取芯样以做进一步试验
10、承包商报送中间交工证书并由监理工程师签认
三、监理重点
1、复核桥位、桩位
2、在流砂地区钻孔应有足够的坍孔措施,最好用长护筒或全护筒防护
3、在地震设防地区,设计者往往考虑液化现象而将桩加长以深入至可靠地层,而粉砂层常夹在两硬土层之间,因此有的施工人员在发现进尺困难时往往认为地质与桩长不符,提出要修改设计此时监理工程师应注意判断,作出合理的指令
4、在沿海地区,混凝土及钢筋往往受到氯离子和硫酸根离子的侵蚀,因此要注意砂和水中氯离子的含量在设计要求采用抗硫酸盐水泥的地方,一定要用抗硫酸盐水泥以防侵蚀
5、在现场要经常检测混凝土坍落度
6、钢筋的焊接应可靠,焊缝要错开
7、下钢筋的焊接要注有维持保护层的措施
8、导管应注意其密封性和插入混凝土的深度,既不能拔脱造成断桩,也不能过多使混凝土流动困难
9、在静荷载试验中要注意确定荷载的终止点,并检验基准梁的可靠性
10、每根桩都必须进行无破损检验
11、在认为桩的质量有问题时,可建议承包商进行钻取混凝土岩芯进行检验第十三章先张法预应力预制梁监理实施细则
一、原材料
1、混凝土祥见混凝土监理实施细则
2、钢丝、钢绞线应符合国家标准GBT5223-
95、GB/T5224-95的要求
二、先张工艺
1、台座承力台座须具有足够的强度和刚度,其抗倾覆安全系数应不小于
1.5,抗滑移系数应不小于
1.3横梁须有足够的刚度,受力后挠度应不小于2㎜在台座上铺设预应力筋时,应防止沾污预应力筋张拉前应对台座、横梁及各项张拉设备进行详细检查,符合要求后方可进行操作
2、张拉同时张拉多根预应力筋时,应预先调整其初动应力,使相互之间的应力一致;张拉过程中,应使活动横架与固定横架始终保持平行,并应抽查力筋的预应力值,其偏差的绝对值不得超过按一个构件全部力筋预应力总值的5%预应力张拉完毕后,与设计位置的偏差不得大于5㎜,同时不得大于构件最知边长的4%预应力筋张拉应符合设计要求,设计无规定时,其张拉程序可按下表规定进行预应力筋种类张拉程序钢筋0初应力
1.05σcon持荷2min
0.9σconσcon锚固钢丝、钢绞线
1、0初应力
1.05σcon持荷2minσcon锚固
2、对夹片式等具有自锚性能的锚具普通松驰力筋0初应力
1.03σcon锚固低松驰力筋0初应力σcon持荷2min锚固表中σcon为张撞的控制应力值,包括预应力损失值先张法预应力筋断丝限制见下表类别检查项目控制数钢丝、钢绞线同一构件内断丝数不得超过钢丝总数的1%钢筋断筋不容许
3、预应力筋放张的砼强度应达到设计要求,设计未规定时,不得低于设计的砼强度的75%
4、预应力筋的放张顺序应符合设计要求,设计未规定时,应分阶段,对称,相互交错地放张在力筋放张之前,应将限制位移的侧模、翼缘模板或内模拆除
5、多根整批预应力筋的放张,可采用砂箱法或千斤顶法,用砂箱放张时,放砂速度应均匀一致;用千斤顶法时,放张宜分数次完成单根钢筋采用拧松螺母的方法放张时,宜先两侧后中间,并不得一次将一根力筋松完
6、钢绞线放松后,可用砂轮锯切断长线台座上预应力筋的切断顺序,应由放张端开始,逐次切向另一端第十四章后张预应力预制梁监理实施细则
一、原材料
1、混凝土详见混凝土实施细则
2、后张法用的预应力钢丝、钢绞线应是符合国家标准GBT5223-
95、GB/T5224-
95、GB/T5223-
95、GB/5224-95的要求
3、预应力钢材孔道的预留方法较多,一般采用波纹管,这种管预埋在混凝土梁中可以随意弯曲且不漏水漏浆孔道上需预留压浆排气孔
4、后张锚头下的垫板钢板,切割与管道相同直径的孔上面有锚固钢筋,__时应与孔道出口中线垂直
二、后张工艺
1、立好一侧模板后,即应装好非预应力钢筋并在钢筋上装好预留管道,管道的__应符合图纸要求的位置,按图示曲线装设,横向位置也必须准确预留压浆排气孔道,并加木塞,以防异特进入孔道
2、浇筑混凝土,并留试样准备做标准养生及同条件养护,过一段时间就要取一组做试验,待同条件养护的试件达到设计强度时即可进行张拉
3、混凝土达到设计强度后即可进行张拉千斤顶最好放在两端同时张拉,所用锚具应经过热处理使之达到洛式硬度HRC55-58千斤顶应经常进行校验,校验时试验机或应力环的精度应达2%后张锚具,大部分是费氏锥式锚使用低碳回火钢丝做成钢筋束,两端在锚头内没梳形板各钢丝应互相平行没有扭结,使每根丝两端都能辨认钢丝张拉在气温+5℃以下不能进行钢丝张拉到控制应力的105%并保持5分钟后,将应力降低到控制应力的100%,并测量钢丝的伸拉度如钢丝伸长量和换算出来的应力与油表指示应力偏差不超过5%,则认为张拉合格,否则应在监理工程师的指导下进行调整张拉合格后即可作开始灌浆的准备
4、孔道灌浆在灌浆前应用压缩空气对孔道进行吹扫,再以每升
0.01Kg氢氧化钙的水清洗耳恭听孔道,然后用压缩空气吹干,所有压缩空气应无油灰浆应用活塞压浆机压进管道,灰浆应从低处压向高处,在最高处开孔排气直至排气孔冒出灰浆为止灌浆要进行两次,使灰浆充满管道,避免管留有半月形空隙灌浆用的灰浆为硅酸盐水泥净浆,水灰比应控制在
0.38-
0.42之间此外可以加入一定量的减水剂,但不得用含有氯化物的外掺剂灰浆强度用100㎜立方体试件标养28天,强度应不小于40Mpa构件温度在+5℃以下时不能进行灌浆,灰浆的温度也不应大于32℃灌浆工作应填写记录
5、封锚在压浆后将锚具周边擦洗干净,然后放置钢丝网,支立模板浇制封锚混凝土,封锚凝土应不低于构件混凝土强度,浇封锚混凝土时应注意构件长度,控制其不超过长度允许值
三、监理程序后张预应力梁的监理程序见图
1、承包商先做好各项准备工作,主要是备好原材料,建设好预制场地,做好大梁底模和底模的基础,准备好模板机具如起重设备等,建好混凝土预拌厂,备好运输设备做好水泥混凝土配合比设计并进行试验复核,连同原材料出厂证件一并报监理工程师审批
2、承包商在做好初步准备工作并经监理工程师批准后,即可编制开工报告开工报告的内容包括制件名称及要供应的桥梁名称、开工日期、计划进度、预期竣工日期、材料、机具、模板、预拌厂、水电供应张拉设备、灌浆设备、锚具等项开工报告经监理工程师审查批准后,即可__开工
3、承包商在备好的底模上支立模板,绊扎预先__过的非预应力筋,按图纸所示位置绑好预应力管道,留好灌浆排气孔,放好锚头垫板、支座垫板等,经驻地监理人员旁站监督并检查后才可进行封模封模前应提醒施工人员注意放好保护层垫块或支架,清扫模内各部位,不得过且过杂物遗留在内
4、浇制混凝土在浇制过程中,监理人员要始终现场旁站,要注意留取试件,一级进行标准养生用以检查混凝土强度,另备若干组随梁做同条件养生,用以控制拆模和张拉
5、现场混凝土达到设计传递强度后,即可通过在孔道中预留的钢丝穿拉预应力钢束,或用特制穿钢束的铁帽,把钢束穿入各孔道并装好锚具和千斤顶,接好路面
6、开动油泵向千斤顶中送油,进行张拉,张拉至钢丝不控制应力的105%,再回放至100%,然后用千斤顶锚固住钢筋和锚头,同时要检测钢筋伸长率并进行核对,整个张拉过程要做好张拉记录(见附表7-9)张拉应按图示程序对称张拉,使梁的受力平衡,避免出现翘曲
7、张拉合格后即可开始灌浆,使孔道内围在钢筋周围都是水泥浆灰浆的抗压强度为40Mpa,用100㎜立方体试块测试,水灰比为
0.38-
0.42灰浆压力最高达
0.7Mpa灌浆时应由排气孔排气,并直到有灰浆从排气孔溢出为止灌浆应重复进行一次,以免孔道不密实而留有空隙
8、灌浆完毕后,即可刷净锚头周围,支立模板浇筑混凝土封锚
9、从支一面侧模、绑扎非预应力钢筋开始至灌浆封锚,监理工程师应始终旁站监督并进行抽查检验
10、封锚以后,承包商即可填写中间交工证书并送监理工程师签认,其后的程序与涵管监理等相同在封锚混凝土强度达到设计强度前,构件不准起吊运输
四、监理重点
1、检查张拉千斤顶油表是否经常进行校对
2、检查张拉过程、预应力建立值、有无断丝滑移现象
3、检验混凝土强度是否达到应力传递强度
4、批准构件的起吊运输
5、检验预留孔道位置是否符合要求后张预应力梁监理程序框图监理程序施工程序预应力张拉记录表工程名称日期施工部位气温张拉束编号混凝土强度钢丝规格编号附图锚具规格编号千斤顶型号编号油表表编号初始张拉设计应力值MPa控制张拉设计应力值锚具锚具力(t)修正系数修正系数压力表读数MPa理论压力表读数MPa理论压力表读数MPa实际压力表读数MPa实际压力表读数MPa备注实际伸拉长值(㎜)实际伸拉长值(㎜)理论计算弹性伸长值(㎜)理论计算弹性伸长值(㎜)张拉技术负责人记录制表预应力孔道(压浆)施工记录工程名称施工单位砂浆稠度气温表格编号砂浆泌水性压浆温度压浆日期序号束号孔号第一次压浆备注压浆冒浆压力MPa实况计(分)时压浆时间停压时间签章张拉技术负责人记录制表后经张拉预应力筋张拉程序预应力筋张拉程序钢筋、钢筋束0初应力
1.05σcon持荷2minσcon锚固钢绞线束对于夹片式等具有自锚性能的锚具普通松驰筋0初应力
1.03σcon锚固低松驰力筋0初应力持荷2minσcon(锚固)其他锚具0初应力
1.05σcon持荷2minσcon锚固钢丝束对于夹片式等具有自锚性能的锚具普通松驰筋0初应力
1.03σcon锚固低松驰力筋0初应力持荷2minσcon(锚固其他锚具0初应力
1.05σcon持荷2minσcon锚固精轧螺纹钢筋直线钢筋时0初应力0σcon持荷2min曲线钢筋时00σcon持荷2minσ(上述程序可反复几次)0初应力0σcon持荷2min注
1、表中σcon为张拉时的控制应力,包括预应力损失值;
2、两端同时张拉时,两端千斤顶升降压、划线、测伸长、插垫等工作基本一致;
3、梁的竖向预应力筋可一次张拉到控制应力,然后于持荷5min后测伸长和锚具张预应力筋断丝、滑移限制数类别检查项目控制数钢丝束和钢纹线束每束钢丝断丝或滑丝1根每束钢绞线断丝或滑丝1丝每个断面断丝之和不超过该断面钢丝总数的百分数1%单根钢筋断丝或滑移不容许注超过表列控制数时,原则上应更换当不能更换时,在许可的条件下,可采取补救措施,如提高其它束预应力值,但须满足设计上各阶段极限状态的要求第十五章桥梁结构物预制__监理实施细则
一、原材料
1、对混凝土及非预应力钢筋等原材料的要求见混凝土钢筋实施细则
2、支座钢板预埋件焊有锚固筋,用A3钢板制做并预埋于预制混凝土中,其大小应能与橡胶支座配合
3、使用橡胶支座时橡胶板式支座,桥梁用盆式支座,支座中的合成橡胶钢材聚四氟乙烯片和不锈钢片材质的__都应符合规范要求
4、桥梁伸缩缝在按装时对已建成桥梁只要剔开混凝土卧进锚筋用混凝土浇灌锚定后,再在两侧铺装沥青混凝土面层,最后在靠近伸缩缝两侧各
0.5m范围浇筑高标号混凝土,等混凝土硬化达到要求强度后,再拆去焊接夹具即成
5、在支座附近要埋设抗震销抗震销用粗钢筋制成,外面加防护套管,上面加帽子管内塞以沥青材料使抗震销在较小震动时可有一定的活动余量,即可防止浇进去造成堵塞,又使钢销不致和混凝土粘在一起另一类抗震措施是挡块,为普通钢筋混凝土,只要照图制作即可
6、桥面后浇混凝土面层,是与预制件同一标号的混凝土,浇筑后放在预制板上面,既能保护预件不受损害,又能与预制混凝__同作用,增加了梁的设计有效高度,而且可起到找平层的作用混凝土配比设计和质量控制与一般混凝土相同
7、排水设施为排除桥__水,每跨都设有排水口,集水口加有铸铁件笆子,或经监理工程师批准使用硬塑料排水管跨高速公路的跨线桥还要沿桥墩设落水管,落水管为铸铁管或硬塑料管
8、桥头锥坡护岸见砌筑工程监理实施细则
9、桥梁构件__后,在两侧应浇制地袱梁梁中除一般钢筋外尚应埋有照明电线管,此管可用镀锌铁管或塑料管,在分歧点或灯柱上,铸铁柱和钢管扶手都应涂以防护油漆,以免生锈
10、__电缆过桥时应在两桥之间装设角架及接线盒,使φ100㎜钢管排在两桥之间空档处穿过先在边桥中预埋铁板,支架角铁弧焊焊上去,φ100㎜钢管在桥两端__分隔带内设连接井,井外用混凝土管块联接
二、监理程序
1、钻孔桩完成后应完成报验验收程序,随后即可支立模板扎钢筋浇筑承台、桥墩、桥台和帽梁
2、准备各项原材料及预制构件,并均应有出厂合格证准备各项机具,并经监理工程师检查落实
3、编制开工报告说明工程地点、规模、开工日期、进度安排、预期竣工日期、拟采用工艺、原材料、机具、劳力、动力供应情况经监理工程师审查落实后加以批准必要时应在报告中附混凝土配合比例
4、采用吊车或架桥机,安排预制板或预制梁__中应装好支座和采用抗震措施,预制板加纵向抗震销,预制梁加抗震挡块板梁应按照图纸设计要求设置支座
5、预制板在__后应铺设钢筋网,浇筑桥面混凝土要注意上下结合,做好结合面的处理
6、预制梁在__后应支模绑钢筋浇筑端横隔梁及翼缘,然后浇__横隔梁、翼缘及1/4跨横隔梁及翼缘桥梁结构的预制件__监理程序框图监理程序施工程序十六钢筋砼板涵监理实施细则根据《公路工程技术标准》、《公路工程质量检验评定标准》、《公路工程施工监理规范》、苏莎路道路工程的有关文件以及建设单位与监理单位签订的监理合同,建设单位与施工单位签订的合同文件,及相关规范等,结合本工程的实际情况,编制钢筋砼板涵监理实施细则,以便于各级监理人员对现场实施有效的监控,确保工程目标的实现
一、技术控制基本要求
1、对原材料的质量要求1)水泥对进场的同厂家、同品质、同编号、同生产日期的水泥以200T为一批验收,每批至少取样一次,做有关试验分析,证实该批水泥各方面均符合标准、规范要求,同时水泥运至工地后应尽快使用,在正常保管情况下,每三个月检查一次,水泥由于受潮或其他原因已变质或不能使用时应从工地运走;2)水采用饮用水;3)碎石对进场的同料原、同级配的碎石,每500M3为一批验收,每批至少取样一次作筛分分析,视比重、容重、含泥重、针、片状含量、压碎指标值等试验,合格后方可投入使用,同时不同来源的集料不得混合或储存在同一料堆,也不得交替使用在同类工程中或混合料中;4)砂对进场的砂,每200M3为一批验收,每批至少取样一次做筛分分析,视比重、容重、含泥量试验;5)外加剂外加剂的使用根据厂商说明,经试验证实,且经监理工程师认可同意后方可使用;6)钢筋
①钢筋品种规格和技术性能应符合国家现行标准规定和设计要求;
②进场钢筋应具有出厂质量证明忆,所用的钢筋应进行抽验;
③钢筋必须按不同钢种、等级、牌号、规格及生产厂家分批验收,不得混杂,且应立牌以示识别,钢筋在运输、储存过程中,应避免锈蚀和污染;7)钢筋的__及__
①__于工程上的钢筋应无灰尘,有的锈蚀、松散锈皮、油漆、油脂或其他物质;
②钢筋均应进行调直后,按图纸形状__,__应准确;
③在施工中以另一种强度牌号或直径的钢筋代替图纸中所规定的钢筋时,应报请监理工程师批准,否则不得替用,光圆钢筋不得代替带肋钢筋;
④钢筋连接点不应设置于最大应力点处,并应使接头交错排列;
⑤钢筋焊接前,必须根据施工条件进行试焊,合格后方可正式施焊,焊工必须有考试合格证,钢筋电弧焊所采用的焊条,其性能应符合低类钢和低合金钢电焊条标准的有关规定;
⑥在构件任一有钢筋焊接接头的区段内,闪光对焊接头的钢筋__在受拉区不应超过钢筋总__的50%同一根钢筋在区段内不得过且有两个接头;
⑦钢筋接头采用电弧焊时,其焊缝长度、宽度、厚度应符合施工规范要求;
⑧现场绑扎钢筋时,搭接长度不应小于表2规定,在变接区,光圆钢筋的绑扎接头末端应设180°弯钩,带肋钢筋绑扎接头末端可不设弯钩;C20C25高于C25Ⅰ级35d30d25dⅡ级45d40d35dⅢ级55d50d45d
⑨在任何情况下,纵面受拉钢筋的搭接长度不应小于300㎜,受压钢筋的搭接长度不应小于200㎜;⑩搭接部分应三处绑扎,即中点及两端,搭接接头的区段内,搭接接头的钢筋__在受拉区不得超过总__的25%,受压区不超过总__的50%,两接头间距不小于
1.3倍搭接长度,为保证保护层厚度,在钢筋与模板间设置垫块8)模板、支架
①模板、支架具有必须的强度、刚度和稳定性,级可地承受施工过程中可能发生的各项荷载,保证结构物各部形状、尺寸准确;
②模板表面平整,接缝严密不漏浆,重复使用的模板应始终保持其表面平整,形状准确,不漏浆,有足够的强度和刚度;
③模板与钢筋__工作应配合进行,妨碍绑扎钢筋的模板应待钢筋__完毕后安设;
④__侧模时应考虑防止模板的位移和凸出,固定在模板上的预埋件和预留孔洞须__牢固,位置准确;
⑤砼浇筑前应对模板涂刷脱模剂;
⑥非承重模应在混凝土强度能保证混凝土表面及棱角不损坏的情况__可拆除,承重模板、支架,应在混凝土强度能承受百重时方可拆除,即达砼设计等级的85%时方可拆除9)混凝土的生产及浇捣
①配制砼所用原材料应符合要求,不同标号砼均应进行试配;
②混凝土最大水泥用量一般不超过500Kg/m3,大体积砼不宜超过300Kg/m3;
③砼的运输能力应适应混凝土结速度和浇筑速度的需要,使浇筑工作不间断并使砼运到浇筑地点时仍保持均匀性和规定的坍落度;
④混凝土应按一定厚度、顺序和方向分层浇筑;
⑤混凝土浇筑用振动器振实时,插入式振动器__间距不应超过振动器作用半径的
1.5倍,与侧模应保持5-10㎝的距离,插入下层混凝土5-10㎝,每一振动部位必须振动到该部位砼密实为止,密实的标点是混凝土停止下沉,不再冒气泡,表面呈现平坦、汽浆;
⑥砼浇筑完成后,应在收浆后尽快予以覆盖和洒水养护10)通道锥坡砌石工艺基本要求
①石料等级应符合图纸规定,应强韧、密实与耐立、压地适当细致、色泽均匀、无风化剥落和裂纹驻结构缺陷;
②石料不得含有妨碍砂浆的正常粘结或有损于外露面、外观的污泥、油质或其他有害物质;
③砂浆强度应符合图纸规定,所用水泥、砂及水应符合规范规定;
④片石的厚度不应小于150㎜,块石大致方正,上下面大至平行,石料厚度200-300㎜,石料宽度及长度应分别为石料厚度的1-
1.5倍和
1.5-3倍;
⑤在砌筑前每一石块均应用干净水浇净并使__饱和,所有石块均应座于新拌和砂浆之上,在砂浆凝固前,所有缝应满浆,石块固定就位;
⑥所有石料应按层砌筑,且先铺砌角隅石及镶面石,然后铺砌帮衬石,最后铺砌腹石;
⑦块石砌体应成行铺砌,并砌成大致水平层次镶面石应按一丁一顺或一丁二顺砌筑,任何层次石块与邻石块搭接至少80㎜,砂浆砌筑缝宽应不大于30㎜,帮衬石及腹石的坚缝应相到错开,砂浆砌筑平缝宽度不应大于30㎜,竖缝宽度不应大于40㎜;
⑧勾缝砂浆等级不得小于砌筑浆等级,勾缝深度不小于20㎜11)涵洞、通道回填基本要求“
①涵洞、通道砼砌体的砂浆强度达到设计强度的70%以上时,方可进行回填,应同时在两侧及基本相同的标高上进行;
②回填材料按图纸及业主下达文件执行,应分层摊铺,并用符合要求的设备压实,每层都应达到所要求的压实度标准
三、质量标准
1、本工程质量目标优良;
2、各实测项目应符合下列表
1、表
2、表3有关规定表1钢筋__及__实测项目项次检查项目规定值或允许偏差检查方法和频率1受力钢筋间距(㎜)两排以上排距±5每构件检查2个断面,用尽量同排梁板、拱肋±10基础、锚碇、墩台、柱±20灌柱桩±202箍筋、横向水平钢筋、螺旋筋间距(㎜)+0-20每构件检查5-10个间距3钢筋骨架尺寸(㎜)长±10按骨架总数30%抽查宽、高或直径±54弯起钢筋位置(㎜)±20每骨架抽查30%5保护层厚度(㎜)柱、梁、拱助±5每构件沿模板周边检查8处基础、锚碇、墩台±10板±3表2钢筋网实测项目项次检查项目规定值或允许偏差检查方法和频率1网的长、宽(㎜)±10用尽量2网眼尺寸(㎜)±10用尽量,抽查3个网眼3对角线差(㎜)10用尽量,抽查3个网眼对角线表3盖板涵、箱涵实测项目项次检查项目规定值或允许偏差检查方法和频率1混凝土和砂浆强度(Mpa)在合格标准内按附录D和F检查2轴线偏位(㎜)明涵20用经纬仪检查,纵横向各2处暗涵503结构尺寸(㎜)±20用尽量3-5处4涵底流水面高程(㎜)±20用水准仪检查洞口2处,拉线检查中间2处5长度(㎜)+100-50用尽量6孔径(㎜)±20用尽量3处7顶面高程(㎜)明涵±20用水准仪检查3处暗涵±
503、外观鉴定要求1)涵身直顺,涵底铺砌密实平整;2)进出口与上下沟槽连接顺适,水流畅通;3)帽石一字墙或八字墙平直无翘油现象;4)涵洞延路面平顺,无跳车现象第17章排水管网工程监理实施细则
一、排水管渠监理工作流程、控制要点、目标及方法,
1、测量放样监理工作流程排水管渠工程测量放样监理流程不合格合格不合格合格
(1)测量监理工作要点1)检查承包人的测量人员对图纸的熟悉状况,测量所需用的有关数据是否正确2)复核性检查临时水准点闭合差,导线方位角闭合差3)检验管渠中线的控制点、中心桩、中心钉高程、坡度板设置位置与高程、沟槽边线4)检查管渠与原有的管渠衔接高程
(2)测量放样质量标准、检测频率及方法1)水准点闭合差为±12L、(mm)(L为水准点之间的水平距离,单位km)2)导线方位角闭合差为±40n,(n为测站数)3)直线丈量测距的允许偏差a、测距小于200m时,允许偏差1/5000;b、测距200-500m时,允许偏差1/_____;c、测距大于500m时,允许偏差1/
200002、排水管渠沟槽开挖监理工作流程(见附图九)
(1)监理工作要点1)检查承包人的进场人员、机具、材料进场情况、现场施工条件、审批开工申请单2)检测开挖断面、槽底高程、槽底预留保护层厚度,检查边坡支护设施3)检查排水、雨、冬季施工措施落实情况4)遇地质情况不良、施工超挖、槽底土层受扰等情况时,应会同设计、业主、承包人共同研究制定地基处理方案、__变更设计或洽商手续
(2)排水管渠沟槽开挖质量标准、检测频率与方法1)槽底土基不得扰动,不得超挖,不得受水浸泡、不得受冻2)排水管渠沟开挖质量监理汇总表,排水管渠沟槽质量监理汇总表序号项目允许偏差检验频率检验方法检查程序认可程序范围点数1槽底高程0,-30两井之间3用水准仪侧量监理人员在场,承包人检测填写报表,由监理员签署评语及姓名须经监理工程师的书面认可2槽底中线每侧宽度不小于规定两井之间6挂中心线用尺量每侧计3点3沟槽边坡不陡于规定两井之间6用坡度尺检验每侧计3点
3、排水管渠地基和基础监理工作
(1)监理工作要点1)检查承包人的人员、材料、机具的进场情况、现场施工条件、混凝土配合比、试块抗压强度、施工工艺、操作规程等技术准备情况,审批开工申请单2)监督承包人按基础处理方案所提要求进行基础处理3)检查槽底保护层开挖,槽底地质状况是否与地质报告相符4)检查垫层平面位置、高程、垫层密实度是否符合设计或规范规定5)检查混凝土管座施工配合比,混凝土抗压强度、模板尺寸、钢筋绑扎是否符合设计要求,模板__是否牢固,混凝土振捣是否密实,混凝土表面蜂窝麻面的程度
(2)地基与基础处理的质量标准、检测频率与方法1)排水管道地基处理应符合设计提出各项标准2)排水管道基础施工质量监理标准与检测频
4、排水管道__监理工作
(1)监理工作要点1)检查承包人的人员、材料、机具进场情况,现场施工准备是否满足预定下管施工方案,安全措施是否完备,混凝土配比、工艺操作规程等技术准备情况,审批开工申请单2)检查排水管道的成品质量、成品出厂合格证,外形尺寸、外观质量检查等内容3)下管前的沟槽检查a、基坑排水;b、混凝土垫层的强度是否符合设计要求;c、槽帮是否有裂缝及坍塌可能;d、槽外堆土是否影响下管;4)下管时安全措施是否落实5)管道__检查a、管道中心、高程、坡度与设计的偏差值;b、相邻节管子的错口量;c、管子稳固质量6)管肩混凝土浇筑质量2排水管道__质量标准、检验频率及方法1)稳管必需牢固,管底不得出现倒坡,管道内不得有泥土、砖、石、木块等杂物2)塑钢缠绕排水管质量检验标准应符合《埋地塑料排水管道工程技术规程》(CJJ143-2010)3)排水管道__的中线、管内底高程、相邻管内底错口的允许偏差尺寸、检验频率等要求排水管道安管质量监理汇总表序号项目允许偏差检验频率检测与认可范围点数检验方法检查程序认可程序1中线位移15两井之间2挂中心线用尺量监理人员在场,承包人检测填报各类报表,由监理人员签署评语及姓名须经专业监理工程师书面认可2△管内底高程D≤1000mm±10两井之间2用水准仪测量D>1000mm±15两井之间2用水准仪测量倒虹吸管±30每道直管4用水准仪测量3△相邻管内底错口D≤1000mm3两井之间3用尺量D>1000mm5两井之间3用尺量
5、排水管接口质量监理工作
(1)监理工作要点1)检查砂浆配合比、强度、工艺操作规程等技术准备工作,审批开工申请单2)检查管端凿毛清洗质量3)检查二次砂浆抹带施工程度施工质量、尺寸偏差是否符合标准4)检查钢丝网的__是否符合设计要求,是否与管座预埋钢丝网连接牢固
(2)排水管道接口质量标准、检验频率与方法1)砂浆抹带接口应分两次施工,第一层施工后,表面应划线槽;第二层施工后,表面应平整压实不得有间断、裂缝、空鼓和脱落现象2)接口缝隙中严禁用砖、石嵌缝3)接口连接方式采用不锈钢箍或电热熔连接
6、检查井施工质量监理工作
(1)监理工作要点1)审批承包人开工申请,主要内容是人员、机具、材料进场情况、现场施工条件是否具备、准备工作是否符合施工__设计中提出的施工方案2)监测材质、砂浆配合比是否满足设计要求3)监测检查井形状、尺寸及相对位置的准确性,预留管及支管的设置位置、井口、井盖的__高程.4)砼检查井应检查砼配合比,模板质量、钢筋质量、砼浇筑振捣质量等
(2)检查井施工质量标准、检测频率与方法1)井壁必须互相垂直,不得有通缝,必须灰浆饱满、平整,抹面压光,不得有空鼓、裂缝等现象;井内流槽应平顺,踏步__牢固,位置准确,不得有建筑垃圾等杂物;井框、井盖必须完整无损,__无损,位置正确2)井身尺寸长、宽、直径均不得超过允许偏差±20mm,检验频率为长、宽各取1点,每座井均取2点;检验方法均用尺量3)检查井的井身尺寸、井盖高程、井底高程等具体要求见下表检查井质量监理汇总表序号项目允许偏差(mm)检验频率检测与认可范围点数检查方法检查程序认可程序1井身尺寸长、宽±20每座2用尺量,长、宽各计一点监理在场,承包人检测填报表,由监理员签署评语及姓名必须监理工程师书面认可直径±20每座2用尺量2井盖高程非路面±20每座1用水准仪测量路面与道路的规定一致每座1用水准仪测量3井底高程D≤1000mm±10每座1用水准仪测量D>1000mm±15每座1用水准仪测量
7、排水管道闭水试验监理工作
(1)监理工作要点1)审查承包人申报进行闭水试验的方案、措施、准备工作是否满足进行闭水试验的要求2)检查试管段堵口封闭质量,管道、井身无因明显缺陷而形成的漏水或严重渗水的部位发现有上述缺陷时,应通知承包人采取有效措施进行修复,直至满足验收要求为止3)监测闭水试验全过程,检查是否按规定程序进行闭水试验,参与测定30min渗水量,评定渗水量是否满足质量检验评定标准
(2)排水管道闭水试验质量标准、检测频率与方法1)排水管道闭水试验质量标准、检测频率与方法,见以下两表排水管道闭水试验质量监理汇总表序号项日允许渗水量检验频率检验方法检查程序认可程序范围点数1△倒虹吸管不大于质量法两次测定的允许偏差每个井段1灌水监理在场,承包人检测填报表,由监理员签署评语及姓名须经监理工程师书面认可2其他管道△D<700mm每个井段1计算渗水量3△D700-1500mm每3个井段抽验1段14△D>1500mm每3个井段抽验1段1注
1、闭水试验应在管道填土前进行
2、闭水试验应在管道灌满水后经24小时后再进行
3、闭水试验的立位,应在试验段上游管道内顶以上2米如上游管内顶至检查口的高度小于2米时,闭水试验水位可至井口为止
4、对渗水量的测定时间不少于30mm
5、表中D为管径
8、沟槽回填监理工作监理工作要点1)根据沟槽不同部位的回填要求、审查承包人的标准击实试验,并与试验监理工程师所作的平行试验进行比较,确定最佳干密度2)监测现场回填土的最佳含水量与土压实后的压实度是否符合沟槽部位回填土的设计要求3)检测分层回填虚铺厚度、碾压遍数、碾压步骤是否符合施工__设计,分段搭接是否符合要求
(2)回填的质量要求、检测频率与方法1)回填土时,槽内无积水2)不得回填淤泥、腐植土、冻土及有机物质3)管顶500mm内不得回填大于100mm的石块、砖块等杂物4)沟槽内不同部位的回填土的不同压实要求
二、雨水井、支管的监理工作流程、控制目标、方法(见附图十三)
1、监理工作要点
(1)根据设计文件的图纸规定,检测井位、支管的定位、定向和高程
(2)检查所使用的井框、井铁箅子及支管的出厂质量,是否符合要求,合格,监理工程师书面认可
(3)随时抽查水泥砂浆的抗压强度;合格,认可
(4)检测雨水井的内外砌筑尺寸及支管接口质量
(5)检验井周、支管回填压实质量
(6)全道工序完成后,应及时检测井口高程,与路边线吻合等情况,并对外观进行检查合格,应签字认可,有缺陷部分应指示承包人修整合格后,再签字认可
2、质量标准、检测频率与方法
(1)雨水井、支管质量监理汇总表雨水井、支管质量监理汇总表序号项目允许偏差(mm)检验频率检验方法检验程序认可程序备注范围点数1井框与井壁吻合10座1用尺量监、承双方选择位置、由承包人检测记录,并填写报表由监理工程师书面认可井周及支管回填必须满足要求2井口高程+10-30座1与井周路面比3井位与路边线吻合20座2用尺量4井内尺寸+20-0座1用尺量5外观检查雨水井内抹面必须平整,不得起壳裂缝井内严禁有垃圾等杂物井框、井箅必须完整无损,__应平整监、承双方检查,承包人记录,并填写报表同上第十八章人行道、坎边石、路缘石的监理实施细则人行道、侧石、缘石的监理工作流程、控制要点、目标及方法:
1、监理工作要点
(1)检测人行道、侧石、缘石板等预制件的半成品规格及外观质量
(2)检查施工放样及高程
(3)检验基底的平整度、整体均匀密实度
(4)检查预制件安砌的水泥砂浆规格
(5)检查现浇水泥混凝土所用的水泥、集料、砂的规格及用量,并对现场浇筑的水泥混凝土或沥青混合料的强度、配合比等进行试验
(6)铺筑完成后,应及时对人行道、侧石、缘石外观、外形尺寸等进行检测,发现缺陷,及时通知承包人进行修整完善
2、质量标准、检测频率与方法运达现场的侧石、缘石及人行道板必须符合以下两表的规定其外观表面平,不得有蜂窝、露石、脱皮、裂缝等现象彩色道块应色彩均匀,线路清晰和棱角整齐预制坎边石、路缘石、平石允许偏差序号项目允许偏差(mm)1混凝土抗压强度平均值不低于设计规定2外形尺寸(长、宽、高)±53外露面缺边掉角长度<20且不多于1处4外露面平整度3安(铺)砌的坎边石、缘石、平石及人行道应符合以下两表的规定外表面坎边石、缘石、平石,必须稳固,并应线直、弯顺、无折角、顶面平整无错牙,坎边石、勾缝应严密,路缘石不得阻水坎边石、路缘石允许偏差序号项目允许偏差(mm)检验频率检验方法范围点数1直顺度10100m1拉20m小线量取最大值2相邻块高差320m1用尺量3缝宽±320m1用尺量4坎边石顶面高程±1020m1用水准仪具测量注粗料石缝宽的允许偏差为±5mm预制块人行道质量监理汇总表序号项目质量标准允许偏差(mm)检验频率检验方法检验程序认可程序范围点数1压实度路床应满足设计规定>90%100mm2用环刀法或灌砂法检验监、承双方选择位置,监理在场,由承包人检验,并填写报表监理工程师书面认可基层>95%2平整度5201用尺量取最大值监、承双方共同选择位置,由取承包人检测记录,并填写报表经监理工程师的书面认可3相邻块高差3201用水准仪测最4横坡应满足设计规定±
0.3%201拉20m小线量取最大值5纵缝直顺10401拉20m小线量取最大值6横缝直顺10201沿路宽拉小线量取最大值7井框与路面高差5每座1用尺量8外观检查铺砌必须平整稳定,灌缝应饱满,不得有翘动现象人行道面层与其他构筑物应接顺,不得有积水现象目测监、承双方共同检查、承包人记录,并填写报表同上第__章挡土墙、防护及其他砌筑工程质量监理实施细则挡土墙质量控制重点砂浆及砌块强度、断面尺寸、顶面高程、底面高程、表面平整度
一、砌筑材料要求原材料系形成实体工程的主要因素,特别挡土墙材料的质量是影响工程质量的重要因素,监理工程师在挡土墙用料中特别监督施工单位1为保证挡土墙的正常使用和经济合理,墙后填料应选择砂土类、碎砾石土填料,注意不能使用冻胀材料2石料应选用结构密实、质地均匀、不易风化且无裂缝的硬质片石石料的抗压强度不小于30Mpa在冰冻及浸水地区,应具有耐冻和抗浸蚀性能片石应具有两个大致平行的面,其厚度不小于15cm其中一条边长不小于30cm,质量不小于30kg砌筑时应敲去尖锐突出部分,放置平稳,分层错缝搭叠砌筑,砂浆填塞应饱满二)、施工过程中质量监理1基坑几何尺寸必须符合设计要求;2地基承载力必须达到设计要求,否则必须处治后才能施工;3墙趾部分的基抗,在基础施工完成后应及时回填夯实,并作成5%外倾斜坡,以免积水下渗,影响墙身稳定4挡墙应错缝砌筑,填缝必须密实,灰浆应填塞饱满5墙体应达到设计强度的75%以上,方可回填墙后填料回填前,应确定填料的最佳含水量和最大干密度根据碾压机具和填料性质,分层填筑压实,压实度应满足设计要求6墙后回填必须均匀摊铺平整,墙后
1.0m范围内应用小型压实机械碾压,分层厚度不得超过
0.2m7墙后地面横坡陡于1:5时,应先处理填方地基再填土,以免填方顺原地面滑动
三、挡土墙的质量评定标准为了保证工程质量,挡墙施工完成后,要求施工单位首先自检,合格后报监理工程师抽检.四)采用钢筋混凝土挡土墙时参照钢筋混凝土工程监理细则实施第__章照明、电力、管线综合工程监理
一、照明、电力、管线综工程慨况
1、照明工程1路灯采用单侧挑臂;90WLED光源__高度9米;配两组太阳能板135W/组36V;配2个蓄电池12V150Ah;含市电互补控制器;配电量远程采集器;配后半夜功率自动降低的电源适配器2路灯电缆道路照明供电电缆采用穿PE100DN100管敷设埋深不小于
0.7米不应破坏原有路面结构;电缆转弯处需设电缆井;手孔井、电缆井和电池井应由UPVC管接至就近雨水检查井或收水井,电缆井侧管高程应高于雨水井侧管高程;过路时改为穿G100热浸锌电缆保护管敷设,钢管埋深不小于
0.8m每回路灯具按abccba......相序跳接.两灯杆之间留一段大概1米左右的电缆采用混凝土包封,不需穿管,以此来减少偷盗电缆现象3安全接地与防雷本工程道路照明配电系统的接地形式采用TT系统,箱变处电气设备金属外壳穿线钢管等均应可靠接地,接地电阻不大于4欧姆,施工时实测,如不满足要求补打接地极箱式变电站接地作法参见04D201-3《室外变压器__》第44页接地装置作法示例
(一)接地、重复接地和灯杆防雷统一考虑,用一根Φ12热浸锌圆钢作为水平接地线与电缆保护管同槽敷设每基路灯的太阳能电池外壳、灯杆、灯具外壳、金属支架等,等电位连接并利用钢筋混凝土基础作为自然接地体,灯杆基础内主筋、预埋螺栓、箍筋、钢垫板可靠焊接,金属灯杆与接地系统做可靠电气连接,重复接地电阻不大于10欧姆,接地电阻以现场实测为准,不满足要求时补打人工接地极桥梁灯杆基础内预埋扁钢与∅12圆钢可靠焊接,在桥梁两侧分别补打一组接地极
2、管沟电力管线监理要点1施工流程施工准备→测量定位→管槽开挖→验槽→基础处理→铺管电缆隐蔽验收→电缆沟回填土→单项工程验收2管沟开挖管沟开挖采用机械开挖,开挖深度不得小于管线埋深深度,管道开挖时,应注意对现有管线的保护基坑挖完后进行验槽,作好记录,监理工程师检测合格后方可进行下一工序的施工3回填土经监理工程验收合格后,进行电缆沟回填,回填采用素土夯实
3、道路照明工程监理要点1照明管沟开挖方法照明管线在绿化带中直埋敷设,覆土厚度
0.7m,敷设时注意避开行道树过路口时设埋设铸铁管保护,照明保护管埋深在
0.7m左右沟槽开挖,先进行测量定位,抄平放线,定出开挖宽度,按放线分段施工沟槽开挖采用机械开挖,槽底土壤严禁扰动,挖槽在接近槽底时,要加强测量,注意清底,不要超挖2管道铺设箱变进出线电缆埋管,根据实际方向进行预埋,保护管的埋设数量应考虑用回路,箱变的排水在其基础底部设一根φ160PVC管将积水排至邻近的道路雨水井,排水坡度为2%路口过路管采用铸铁管过路,对于先破除一半的路口,在铺设管道时应用8#铁丝导线穿通管线,在管头用纱布包裹,以防管口堵塞3照明接线井及路灯基础施工1井身用100#砂浆砖砌体,内墙粉层用12水泥砂浆抹面,厚度10mm,不封井底以利渗水2井框井盖用φ700铸铁套件;3井表面与人行道标高一致,并保持人行道外观的一致性;4路灯基础9m~8m、10m~13m灯具灯杆基础混凝土分别为C
25、C20钢筋混凝土,施工全部采用机械搅拌,机械振捣,人工配合随捣随压实赶光5防撞护栏、波形护栏上的灯杆基础的预埋杆件,随护栏施工时预埋第__一章交通设施质量监理
1、道路交通标志控制监理1各种材料在订购前,应向监理工程师提供生产厂家的资质及产品合格证明、使用说明和规定等资料,经审查同意后方可订货材料进场应向监理报验,并抽样试验,合格后方可使用2标志的位置应符合设计要求,__的标志与交通流方向成直角;在曲线路段,标志的设置角度应由交通流的行进方向来确定3标志应向后果旋转5度,以消除标志表面产生的眩光门架标志的垂直轴应向后倾成一定角度标志板内缘距上路肩不得小于25cm4标志基础的开挖及浇筑砼、锚固螺栓的预埋,都应经监理工程师批准后才可施工,其施工要求与砼工程施工的监理要点相同5钢支架的制作应符合设计和规范的规定钢支架的架设应在基础砼强度达到设计要求之后,并事先报请监理工程师批准6标志板的外形尺寸偏差不大于±5mm;四边互相垂直,垂直度偏差不大于±10mm;平面翘曲偏差不大于±3mm/m板面应无裂纹和划痕及明显的颜色不均匀,在任何__为
0.25m2表面上不得有一个或一个以上总__大于10mm2的气泡7里程标、百米标、公路界碑、安全标、固定标志根据设计及《道路交通标志和标线》(GB5768-1999)规定制作和设置8__标志板时,应事先获得监理工程师的批准标志的固定方法应符合图纸要求标志__完毕后,监理工程师检查所有标志,以确认在白天和夜间条件下标志的外观、视认性、颜色、镜面眩光等是否符合图纸要求
2、道路交通标线控制监理1路面标线材料应能满足在路面上耐久使用的要求,承包人应向监理提供生产厂家的资质、产品合格证明资料,对每批材料在进场时进行抽样试验2产品存放时应保持通风、干燥、防止日光直接照射,并应隔绝火源,夏季温度过高时应设法降温;运输过程中应防止雨淋、日晒;采用集装箱运输;产品超过贮存期的应按《路面标线涂料》规定的项目进行检验,不合格的,不得使用3设置标线的路面表面应清洁干燥,无松散颗粒、灰尘、沥青、油污或其他有害物质4涂料在容器内加热时,温度不得超过产品使用说明中的最高限制温度,喷涂于路面时的温度亦应符合说明书的要求;喷涂施工应在白天进行,雨天、尘埃天、风天、温度低于100℃时应暂停施工;喷涂应使用自行式机械5标线的宽度、虚线长及间隔、点线长及间隔、双标线的间隔、特殊标线的图案、标记如箭头及字母等的尺寸均应符合设计图纸及规范的规定;所有标线均应顺直、平顺、光洁、均匀,具有精美外观;湿膜厚度符合图纸要求6喷涂标线作业时,应有交通安全措施,设置适当警告标志阻止车辆及行人在作业区内通行,防止将涂料带出或形成车辙,直至标线充分干燥7标线以外的道路被标线材料污染应及时处理
(8)根据设计图主道和辅道之间行车道中间分割带为园形,容易造成车辆逆行,建议采用浆砌大卵石砌筑车辆导行设施防止车辆逆行,以保证安全第__二章绿化、景观工程质量监理重点对绿化、景观工程质量实行监理,提高绿化种植成活率,改善绿化景观,节约绿化建设资金,创造良好的生态环境,确保绿化工程质量
1、施工准备阶段的质量监理1施工现场准备工作的监理要点1检查施工单位的资质和有关审批文件是否齐全,检查施工人员、机械等进场情况2根据批准的绿化工程设计及有关文件,在开工前应__设计单位和施工单位进行设计交底,如发现施工现场与设计图纸不符之处,应提交设计单位出具设计变更3检查施工单位编制的施工计划书,其中应包括
①施工程序和进度计划;
②各工序的用工数量及总工日;
③工程所需材料进度表;
④机械与运输车辆和工具使用计划;
⑤施工技术和安全措施;
⑥施工预算;
⑦大型及重点绿化工程应编制施工__设计4做好地下管线、主要建筑物、道路工程等与绿化工程有关的工程调查,尤其是城市建设综合工程中的绿化种植,应在这些工程完工后进行5整地绿化工程施工多在道路工程或者建筑工程等完工后进行,一般遗留的场地多数凹凸不平,特别是雨后积水难以排除,势必影响将来植物的生长,因此,绿化工程在开工前应进行整地工作
①公路绿化场地应依照绿化设计的要求先用推土机等机械设备将场地粗略整治之后进行灌水,使得土壤自然下沉将坑洼不平的地方暴露出来,防止将来土壤塌陷,难于补救,待土壤干燥之后再平整至绿化设计要求;
②对于路桥区域,由于施工后场地多为生土,植物在其上面生长非常困难,此时应该换土,平整场地应用人工进行2种植材料的选择要点1种植材料,应根系发达,生长茁壮,无病虫害,规格及形态应符合设计要求;2铺栽草坪用的草块及草卷应规格一致,边缘平直,杂草不得超过5%,草块土厚度宜为3-5cm,草卷土层厚度宜为1-3cm;3播种用的草坪、草花、地被植物种子,应注明品种、品系、产地,生产单位、采收年份、纯净度及发芽率,不得有病虫害,自外地引进的种子应有检疫合格证,发芽率达90%以上方可使用
2、绿化工程施工阶段的质量监理1种植穴、槽的挖掘质量监理要点1种植穴挖掘前应了解地下管线和隐蔽物埋设情况;2检查种植穴、槽的定点放线应符合设计要求,位置准确,标记明显,定点时应标明中心点位置,种植槽应标明边线;3坑径一般可比规定的根系或土球直径大20-30cm,如遇土质过黏、过硬或含有有害物质如白灰、沥青等,应加大坑径1-2号;4挖坑的坑壁要随挖随修使其成直上直下,不要成锅底形;5在斜坡处挖坑,应先做成一个平台,平台应以坑径最低规格为依据,然后在平台上挖坑2树土种植质量的监理要点1检查种植树苗的品种、规格是否符合设计要求;2栽树时种植深度应与原种植线一致,注意行、列应在一条线上,相邻树苗株距均匀,树木保持直立,不得倾斜;3种植裸根树木,应将种植穴底填土成半圆土堆,植入树木填土至1/3时,应轻提树干,使根系舒展,并充分接触土壤,随填土分层踏实;4栽植带土球树木,要尽量提草绳入坑,摆好位置和高度后用土铲放稳,再剪断腰绳和__,栽绿篱时,如土球完整、土质坚硬,应在坑外将包打开提干捧坨入坑,若坑内拆包,应尽量将包装物取出后,方可分层填土踏实;5树土种植后浇水、支撑固定应注意
①种植后应在大于种植穴直径周围,筑成高10-15cm的灌水土堰,堰应筑实不得漏水;
②种植树木的当日应浇透第一遍水,以后根据温度等情况及时补水;
③浇水时应防止因水流过急冲刷__根系,若浇水后出现土壤沉陷,致使对树木倾斜,应及时扶正、培土;
④对于人员集散较多的__、人行道,树木种植后应铺设透气护栅;
⑤种植胸径5cm以上的乔木,应设支柱固定,支柱应牢固,绑扎树木处应夹垫物,绑扎后树木应酬保持直立
⑥建议种植具有特色的苗木乔木胸径宜在5cm以上并在中间分割带内适当摆设大直径卵石,形__造景观第__三章安全文明监理细则监理的工作内容熟悉和掌握相关法规、规章、规定,审查承包单位的安全文明施工保证体系,检查、督促承包单位严格执行安全保证体系,做好安全文明施工预警和事故处理监督和帮助承包商依法加强工程安全文明生产管理、执行安全生产责任制度、采取有效措施防止伤亡和其他安全生产责任事故发生
1、熟悉和掌握相关的法规、规章及规定
1.1国家、地方__有关安全文明施工的法规,如安全生产劳动保护的法规、安全技术规程、工业卫生标准和安全生产规章制度、安全施工管理条例等
1.2海口市工程建设安全生产、文明施工管理规定、合同文件等
2、审查安全文明施工保证体系的全面性、科学性和合理性安全文明施工保证体系必须包含下列内容
2.1安全文明管理__机构__机构必须健全,承包单位的项目经理必须是安全文明施工的第一责任人,真正做到__到位,__带头,全员参加
2.2安全文明施工目标(或责任)必须明确并且层层分解到班组甚至到人
2.3安全文明施工管理或措施,包括
2.
3.1安全文明施工教育和培训安全法规、规章、规定学习,日常安全教育,安全操作培训、特殊工种培训、市容环境卫生和消防安全知识的教育和培训
2.
3.2安全文明施工管理制度安全文明施工制度、措施、奖罚标准等
2.
3.3__安全文明施工活动如每周定期或每月定时的安全活动、安全无事故活动、文明施工竞赛、安全文明总结整改等
2.
3.4安全文明施工自行监督制度执行情况、措施执行状况、重点部位防范等检查,按“三不放过”分析处理事故
3、承包单位的自检制度承包单位安全管理状况(或措施)及防护
3.1临时用电安全
3.2施工机械及其辅助设备操作安全
3.3保卫和消防保卫人员要充足;保卫制度要落实;消防设施、通信要完备
3.4承包单位文明施工和管理措施
3.5施工现场的布置和场地管理道路(安全通道)、作业场地、材料堆放、弃土临放等须规划有序
3.6工地卫生管理垃圾、污水、鼠害等管理
3.7环保管理生产、生活用水,施工排水等
3.8噪音和尘土控制
3.9现场医疗设备和急救医护人员的配备
4、安全教育与培训
4.1安全教育和培训,是让所有管理人员和现场操作员掌握安全生产知识的前提和保证,能够提高管理人员的安全生产意识和安全管理水平,以及操__遵章守纪、自我保护和提高防范事故的能力它应贯穿施工生产的全过程,覆盖施工现场的所有人员,确保未经过安全生产教育培训的人员不得上岗作业
4.2安全教育和培训的内容
4.
2.1施工管理人员的安全专业技能;
4.
2.2岗位的安全技术操作规程;
4.
2.3施工现场的安全规章、文明施工制度;
4.
2.4特种作业人员安全技术操作规程及措施;
4.
2.5新工艺、新材料、新技术、摩擦设备实施中特定的安全技术规定;
4.
2.6安全保证计划中针对性安全措施要求;
4.
2.7特定环境中的安全注意事项;
4.
2.8对潜在的事故隐患或发生紧急情况下,如何采取防范及自我解救措施;
4.
2.9节假日前后、上岗前、事故后、工作对象改变时、应进行针对性的安全教育
4.3施工现场要有较浓的安全宣传气氛,有醒目的安全标语、警告标志牌和指示牌;大中型机械设备有安全操作规程;作业人员必须穿戴与其工程相适应的个人防护用品;特殊工程必须持证上岗,并有安全员巡视检查
4.4项目经理、安全员等施工管理人员应持证上岗现场作业人员必须经过安全培训和岗前教育新进民工或转岗民工也要经过安全培训,方可上岗作业
4.5在作业前,要根据施工工艺对施工人员进行针对性的安全技术综合交底,要有书面记录和双方签字手续
4.6施工班组必须每周开展一次安全学习交流活动;每天作业前要进行有针对性的安全交底;每逢节假日应根据气候的特点进行针对性的安全教育教育内容要记录在案
5、安全文明施工预警和事故处理
5.1安全生产,必须“警钟长鸣”,监理工程师要坚持以预警和预防为主的原则,一经检查发现有安全隐患,就应该在定期的周例会上或者专门__的安全会议上,提出口头或书面警告,责成承包单位整改
5.2无论是什么原因,对发生安全事故的,监理工程师有权按以__式处理
5.
2.1下达停工检查,限时整改,杜绝隐患
5.
2.2驱逐不遵守安全法规的人员,未经监理工程师书面同意,不得在本工地再次雇用
5.
2.3协助业主、承包单位、劳动部门分析事故原因和责任,商定事故处理的办法;提出安全文明施工的整改建议,检查承包单位的整改效果
6、安全文明施工控制工作流程安全文明施工控制工作流程图见下图
7、施工防火安全管理
7.1坚持安全消防检查制度,防止事故发生;
7.2督促施工单位落实防火交__度特别是焊接、油漆等易燃危险作业时,要有具体的防火要求;
7.3现场使用明火作业时,必须__动火申请,经批准后才能动火动火时必须有专人值班监护,周围无易燃物进行高空电焊作业,必须在其__采取相应隔离措施,并设专人跟焊和监管,不得使用火种从高空散落,防止事故发生
7.4现场设有专门的消防灭火器材和系统,并有消防专用电缆电源
7.5消防系统做到布局合理,经常维护、保养,保证消防器材灵敏有效
8、安全应急措施
8.1施工单位现场应与有关单位的密切__,了解附近医疗、消防、公安、交通、电力、燃气部门以及街道派出所__、地址,以便发现情况及时__
8.2做好现场消防物品准备,定期检查和更换消防器材,配备各种安全防护用具
8.3督促施工单位加强现场安全事故应急处理的培训以及灭火知识教育
8.4督促施工单位制定重大安全事故应急救援措施,建立应急救援体系
8.5发生重大安全事故后立即下达停工令,责令施工人员撤离现场,严格保护事故现场,__抢救、防止事故扩大
9、安全事故的调查与处理
9.1施工企业发生安全事故后,应及时报告项目主管__,再根据事故的严重性上报有关部门,以便尽快得到妥善处理
9.2弄清事故的原因,收集与事故有关资料,最大程度地采取补救措施,将损失降低到最小程度,保证项目的顺利完成
9.3协助安全生产监督管理部门进行事故调查和处理
10、文明施工管理
10.1施工过程中,监理有权阻止违反文明施工规定的不文明行为,提出整改,直至落实为止承包人应成立文明施工__小组,并配有专职文明施工人员,经常检查文明施工情况
10.2督促施工总承包人对施工现场的施工设备、材料堆放、场地道路、生活设施进行统一合理布局,并纳入施工__设计,制定文明施工制度,由项目经理__实施各分包单位应严格执行总包人的规定建设单位应支持协助施工总承包人的文明施工工作,承担有关义务
10.3督促施工现场实行封闭施工施工现场四周除人员、车辆进出口通道外,其余周边应按规定设置连续封闭的围墙位于道路两旁的建设工程从第2层施工开始,必须采用合格的安全网进行全封闭施工
10.4施工现场主门右侧必须悬挂施工标牌施工标牌应标明工地项目名称、建设单位、设计单位、施工单位、项目经理的姓名、开竣工日期及监督__
10.5施工现场的管理人员必须在胸前佩带个人身份标卡,作业工人也应佩带个人身份标卡标卡由总承包单位统一制作,标卡应标明人员姓名、本人照片、工种或职务、所属单位管理人员和施工作业人员的标卡应分颜__别
10.6施工现场应设置连续、通畅的排水设施和其他应急设施,防止泥浆、污水、废水直流或堵塞排水通道和市政排水
10.7施工现场应设置洗车槽出入工地的机动车辆必须在工地冲洗干净后,方允许上路行驶对运输车辆出车前进行检查、覆盖,以保证运输时不至于洒落路面、污染路面,对洒落路面的混合料即刻进行清理,要求运输时派专人进行检查对施工作业机械,运输车辆作业时所产生粉尘进行控制,并定期对施工现场周围地面进行淋水,减少灰尘对周围环境的污染同时做好对城市绿化、地下管线、地下文物的保护
10.8工程所在地建设行政主管部门应根据施工现场周围环境情况对使用高噪音机械做出禁止限制措施,要求承包商控制噪声,减少施工机械、施工作业、施工运输车辆特别是夜间施工所造成的对附近居民的影响,确需进行夜间施工时,采取必要的减噪措施,同时报经主管部门批准
10.9施工现场应设置统一的__食堂,食堂位置原则上应远离厕所、污水沟、垃圾等污染源20米以上,有合格的可供食用的清洁水源和畅通的排水设施食堂管理符合卫生标准炊事员和茶水工上岗持有效的健康证明工地应设茶水亭和茶水桶做到有盖、加锁和有标志夏季施工应有防暑降温措施
10.10工期一年以上的施工现场建筑工人宿舍应使用永久、半永久建筑房屋或活动板房,并具备良好的防潮、通风、采光性能,人均床铺占有__不小于2平方米,并进行适当分隔男女宿舍和淋浴室应能满足施工高峰期的需要建筑工人宿舍应有管理制度,并落实治安、防火、卫生、计生管理责任人
10.11施工现场应设置职工厕所,厕所应有简易化粪池或集粪坑,并加盖定期喷药厕所内必须有水源可供冲洗,落实每日有专人负责清洁工地应设立生活垃圾桶,并每日清运
10.12承包人应当做好施工现场安全保卫工作,采取必要的防盗、防火措施建设单位应在施工方案确定之前,会同设计、施工单位和市政、防汛、公用、邮电、电力等有关部门(单位),对可能造成周围建筑物、构筑物、防汛设施、地下管线损坏或堵塞的建设工程进行现场踏看,并制订相应措施,保证施工安全进行
10.13建设工程竣工后,承包人应在一个月内(市政道路工程在通车半个月内)拆除工地围栏,安全防护设施和其他临时设施,并将工地及四周环境清理整洁,做到工完料净、场地清总监理工程师总监理工程师代表绿化景观专业监理水电__专业监理桥涵工程专业监理道路交通专业监理对施工部门测量工作进行监督、检查、旁站、复测各工程开工前施工部门进行施工放样并通知监理对测量放样报验单及质量检验报告单认真审查认定施工报验控制工程线位、标高、尺寸进行监督、检查、认定工程施工过程中对放样的方法、坐标及放样数据检查及必要复测工程分项开工申请报告、测量放样报验单、现场质检报告对工程完工成品进行位置、尺寸、标高进行检查、测量,并提出各单位工程的测量成果资料验收确认开工报告审批开工报告清理现场现场检查按照规范要求检查原材料质量自检原材料质量旁站并以15%的规范频率检查分层填筑单独或与承包人共同验收,合格后填质检单自检并申报验收根据质检单、开工申请及测试资料签认分项、分部报验单审查复核测量放线测定桩位备好材料、机具并自检,提供混凝土配比等检查抽验复核审查批准资料报验钻进成孔旁站检查检查抽验下钢筋笼及焊接旁站检查下导管浇混凝土工程检查和混凝土质量检查做无破损检测审查签认资料报验熟悉图纸,准备资料、机具模板、底模,提出混凝土配合比检查复核并批准原材料及混凝土配合比资料报审审查批准在底模上支模绑扎非预应力钢筋及留孔道心旁站监督抽查浇筑混凝土检查混凝土强度自检混凝土强度穿预应力钢筋旁站检查张拉锚固灌浆封锚检查签认资料报审准备材料、机具,包括预制构件检查抽查报验审查批准__支座和抗震措施__预制板__预制梁旁站审查工序验收浇端横隔梁浇筑桥面板浇__及1/4跨横隔梁检查桥面及横隔梁混凝土强度浇桥面连续接缝做桥面排水浇地袱装栏杆及照明导管装__导管及伸缩缝审批签认报验验收混凝土级别钢筋级别测量放样开工申请单承包人测量前熟图纸做好准备工作监理工程师审核核对水准点方位角坡度板承包人管渠中线、高程、附属构筑物位置、支管位置质量验收报验单承包人现场检测专业监理工程师监理工程师审批返工签认验收资料监理工程师安全文明保证体系(承包单位)检查监督“安全保证体系”实施(监理工程师)安全文明施工预警和事故处理(监理工程师)审查监理工程师审批(业主)不合格合格修正PAGE。